PENYEIMBANGAN LINTASAN PRODUKSI RIBBED SMOKE SHEET UNTUK MENINGKATKAN EFISIENSI LINTASAN MENGGUNAKAN METODE THEORY CONSTRAINT (Studi Kasus di PT. Perkebunan Nusantara IX, Salatiga)

Harianja, Novri Yohannes (2023) PENYEIMBANGAN LINTASAN PRODUKSI RIBBED SMOKE SHEET UNTUK MENINGKATKAN EFISIENSI LINTASAN MENGGUNAKAN METODE THEORY CONSTRAINT (Studi Kasus di PT. Perkebunan Nusantara IX, Salatiga). Other thesis, UPN "Veteran" Yogyajarta.

[thumbnail of Daftar Isi.pdf] Text
Daftar Isi.pdf

Download (132kB)
[thumbnail of Abstrak_Novri Yohannes Harianja_122180097.pdf] Text
Abstrak_Novri Yohannes Harianja_122180097.pdf

Download (67kB)
[thumbnail of Cover_Novri Yohannes Harianja_122180097.pdf] Text
Cover_Novri Yohannes Harianja_122180097.pdf

Download (62kB)
[thumbnail of Lembar Pengesahan_Novri Yohannes Harianja_122180097.pdf] Text
Lembar Pengesahan_Novri Yohannes Harianja_122180097.pdf

Download (290kB)
[thumbnail of Skripsi Lengkap_Novri Yohannes Harianja_122180097.pdf] Text
Skripsi Lengkap_Novri Yohannes Harianja_122180097.pdf
Restricted to Repository staff only

Download (2MB)
[thumbnail of Daftar Pustaka.pdf] Text
Daftar Pustaka.pdf

Download (286kB)

Abstract

x
ABSTRAK
PT. Perkebunan Nusantara IX merupakan salah satu Badan Usaha Milik
Negara (BUMN) yang bergerak di bidang manufaktur pengolahan karet untuk
diproduksi menjadi Ribbed Smoke Sheet (RSS) terletak Kota Salatiga, Jawa
Tengah. Terdapat beberapa hal yang belum sesuai dengan perusahaan yaitu lintasan
yang kurang efisien disebabkan oleh target perusahaan yang terlalu tinggi
dibandingkan dengan output yang dihasilkan, kemudian proses produksi terdapat
ketidakseimbangan lintasan, yang dimana masih ditemukan penumpukan
bahan/barang dalam proses dibeberapa stasiun kerja sehingga produksi aktual tidak
memenuhi target produksi dan perusahaan mengalami kesulitan memenuhi
permintaan pasar. Sehingga perlu dilakukan penyeimbangan lintasan untuk
menjawab permasalahan tersebut.
Peningkatan efisiensi keseimbangan produksi dapat diperoleh dengan cara
menyeimbangkan lintasan dengan menggunakan metode theory constraint
ditujukan untuk mengurangi waktu menganggur dan penumpukan barang, sehingga
proses produksi menjadi lebih efisien. Metode yang dapat digunakan adalah
CPM/PERT. Langkah-langkah yang digunakan yaitu dengan mengelompokkan
elemen kerja ke dalam stasiun kerja, kemudian menghitung nilai beban kerja,
efisiensi lintasan, smoothing index dan balance delay yang kemudian dibandingkan
berdasarkan kedua metode tersebut.
Hasil yang diperoleh agar lintasan produksi RSS memiliki nilai efisiensi
lintasan yang tinggi berdasarkan perbandingan metode CPM/PERT, sehingga saran
untuk lintasan produksi Ribbed Smoke Sheet (RSS) agar nilai efisiensi lintasan
tinggi mengikuti metode CPM/PERT adalah adalah membuat 3 stasiun kerja
sehingga didapatkan nilai efisiensi lintasan sebesar 85% dan meningkat sebanyak
21% dari nilai efisiensi lintasan yang awal yaitu dari 64% menjadi 85%, kemudian
untuk nilai idle time berkurang dari awalnya 4,66 menit menjadi 1,51 menit, untuk
nilai Balance Delay juga berkurang dari awalnya 37% menjadi 16%, dan untuk nilai
Smoothing Index juga berkurang dari awalnya 3,3 menit menjadi 1,08 menit.
Kata Kunci : Theory Constraint, Stasiun Kerja, Line Efficiency, Ribbed
Smoke Sheet
xi
ABSTRACT
PT. Perkebunan Nusantara IX is a State-Owned Enterprise (BUMN)
engaged in manufacturing rubber processing to produce Ribbed Smoke Sheet (RSS)
located in Salatiga City, Central Java. There are several things that are not in
accordance with the company, namely the inefficient trajectory caused by the target
company which is too high compared to the output produced, then the production
process has conflicts, where materials / goods are still found that are sucked in the
process at several work stations so that actual production does not meet production
targets and companies find it difficult to meet market demand. So it is necessary to
balance the trajectory to answer these problems.
Increasing the efficiency of the production balance can be obtained by
balancing the lines using the theory constraint method which is intended to reduce
idle time and balance goods, so that the production process becomes more efficient.
The method that can be used is CPM/PERT. The steps used are by grouping work
elements into work stations, then calculating the value of workload, flow efficiency,
smoothing index and balance delay which are then compared based on the two
methods.
The results obtained are that the RSS production line has a high track
efficiency value based on a comparison of the CPM/PERT method, so the
suggestion for a Ribbed Smoke Sheet (RSS) production line so that the track
efficiency value is high following the CPM/PERT method is to create 3 work
stations so as to obtain a trajectory efficiency value of 85% and increased by 21%
from the initial trajectory efficiency value from 64% to 85%, then for the idle time
value to be reduced from the initial 4.66 minutes to 1.51 minutes, for the Balance
Delay value also reduced from the initial 37% to 16%, and for the Smoothing Index
value also reduced from the initial 3.3 minutes to 1.08 minutes.
Keywords : Theory Constraints, Work Station, Line Efficiency, Ribbed
Smoke Sheet

Item Type: Thesis (Other)
Uncontrolled Keywords: Theory Constraints, Work Station, Line Efficiency, Ribbed Smoke Sheet
Subjects: Q Science > QD Chemistry
Divisions: Faculty of Engineering, Science and Mathematics > School of Engineering Sciences
Depositing User: Eko Yuli
Date Deposited: 29 May 2023 06:32
Last Modified: 29 May 2023 06:32
URI: http://eprints.upnyk.ac.id/id/eprint/35735