KAJIAN TEKNIS PRODUKSI ALAT GALI-MUAT DAN ALAT ANGKUT DI BUKIT 6 WILAYAH TAMBANG UTARA PT. ANTAM

ARIVANDY, ANDHIKA YONA (2015) KAJIAN TEKNIS PRODUKSI ALAT GALI-MUAT DAN ALAT ANGKUT DI BUKIT 6 WILAYAH TAMBANG UTARA PT. ANTAM. Other thesis, UPN "Veteran" Yogyakarta.

[thumbnail of ABSTRACT 112080186.pdf]
Preview
Text
ABSTRACT 112080186.pdf

Download (6kB) | Preview
[thumbnail of SKRIPSI-112080186.pdf] Text
SKRIPSI-112080186.pdf
Restricted to Repository staff only

Download (1MB)

Abstract

PT. ANTAM The production of this mechanical equipment combination is not reach the
company production target. Current production capability is 41.377 ton/month.
This happened because a lot of wasted work time, which could be avoided and
can not be avoided. These contraints reduce work time effectively so that
efficiency is low.
Improving production can be done by improving the effective working
time, addition of mechanical equipment or change the mechanical. With the
addition of 2 unit Nissan CWT 432 HTRA dumptruck conveyance incfreased to
60.269,55 ton/month. Monitoring the schedule time in order to achieve the desired
production targets should be done so that the production target would be reached.

Item Type: Thesis (Other)
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: Faculty of Engineering, Science and Mathematics > School of Engineering Sciences
Depositing User: Eko Yuli
Date Deposited: 11 May 2016 03:27
Last Modified: 11 Oct 2022 01:47
URI: http://eprints.upnyk.ac.id/id/eprint/632

Actions (login required)

View Item View Item