SALSABILA, MAURA (2021) KAJIAN TEKNIS SISTEM PENYALIRAN PADA TAMBANG BATUBARA PT. MANGGALA USAHA MANUNGGAL JOBSITE PT. BARA ANUGERAH SEJAHTERA, MUARA ENIM, SUMATERA SELATAN. Diploma thesis, UPN "VETERAN" YOGYAKARTA.
![]() |
Text
Draft Maura Salsabila - 112160170.pdf Restricted to Repository staff only Download (21MB) |
Preview |
Text
Abstrak (1).pdf Download (100kB) | Preview |
Preview |
Text
Daftar Pustaka (2).pdf Download (94kB) | Preview |
Preview |
Text
Halaman judul.pdf Download (125kB) | Preview |
Preview |
Text
Halaman pengesahan.pdf Download (566kB) | Preview |
Abstract
v
RINGKASAN
PT. Manggala Usaha Manunggal merupakan perusahaan yang bergerak
pada bidang usaha jasa pertambangan batubara yang dipercayai oleh PT. Bara
Anugerah Sejahtera untuk melakukan kegiatan penambangan batubara. Terletak di
Kecamatan Lawang Kidul dan Kecamatan Tanjung Agung, Kabupaten Muara
Enim, Provinsi Sumatera Selatan. Sistem penambangan yang dilakukan
menggunakan sistem tambang terbuka dengan metode Stripe Mine. Pada awal tahun 2020 terjadi luapan air di ceruk (sump) bagian Utara. Hal
ini disebabkan karena pemompaan yang tidak berjalan kontinu dan kolam
pengendapan yang tidak dapat mengalirkan air ke badan sungai. Sehingga
mengganggu kegiatan operasi penambangan. Berdasarkan masalah tersebut, maka
perlu dilakukan kajian sistem penyaliran tambang dengan mengkaji curah hujan, penentuan daerah tangkapan hujan (catchment area), perhitungan debit air
limpasan yang masuk kedalam pit, kondisi pemipaan dan pemompaan serta kajian
kolam pengendapan. Berdasarkan analisis data curah hujan harian selama 10 tahun (2010-2019), diperoleh curah hujan rencana sebesar 132,11 mm/hari. Berdasarkan perhitungan
dengan rumus Mononobe, didapatkan intensitas curah hujan sebesar 45,79
mm/jam dengan periode ulang hujan 3 tahun yang didapatkan berdasarkan
perhitungan persen resiko hidrologi. Luas daerah tangkapan hujan pada lokasi
penelitian dibagi menjadi tiga, sebagai berikut : DTH I = 0,0913 km2
, DTH 2 =
0,5944 km2
, DTH 3 = 0,2346 km2
. Total debit air limpasan sebesar 9,55 m3
/detik. Sistem pemompaan menggunakan pompa KSB DND H150 dengan
kebutuhan total head sebesar 74,52 meter dan Selwood H150 70,80 meter. Sistem
pemipaan menggunakan pipa HDPE (High Density Polythilene) dengan ukuran
diameter pipa 8 inch sepanjang 372 meter dan 407 meter. Pada saat penelitian
sistem pemompaan tidak berjalan kontinu karena TSS yang tinggi pada kolam
pengendapan. Sehingga dibentuk sebuah kolam pengendapan 1 untuk
mengendapkan sebagian material padat yang terikut oleh air dari ceruk sebelum
memasuki kolam pengendapan. Nilai TSS maksimal yaitu 3.580 mg/L. Kolam
pengendapan terdiri dari 1 kompartemen dengan kapasitas total 1.125 m3 dengan
waktu pengerukan setiap 116 hari sekali.
vi
SUMMARY
PT. Manggala Usaha Manunggal is a company engaged in the coal mining
services business which is trusted by PT. Bara Anugerah Sejahtera to carry out
the coal mining activities. It is located in Lawang Kidul District and Tanjung
Agung District, Muara Enim Regency, South Sumatra Province. The mining
system is carried out using an open pit system with the Stripe Mine method. At the beginning of 2020, there was an overflow of water in the northern
sump. It is because the pumping system is not running continuously and the
settling pond cannot drain water to the river . So that it disrupts mining
operations. Based on this problem, it is necessary to study the mine drainage
system by assessing rainfall, determining the catchment area, calculating the
discharge of runof water, piping and pumping conditions and assessing the
settling pond. Based on the analysis of daily rainfall data for 10 years (2010-2019), the
planned rainfall was 132,11 mm / day. Based on calculations with the Mononobe
formula, the rainfall intensity is 45,79 mm / hour with a 3-year return period of
rain based on the calculation of the percent of hydrological risk. The area of the
catchment area at the research location is divided into three area, as follows:
DTH I = 0.0913 km2
, DTH 2 = 0.5944 km2
, DTH 3 = 0.2346 km2
. The total runof
discharge is 9.55 m3
/ second. The pumping system uses the KSB DND H150 pump with a total head
requirement of 74,52 meters and Selwood H150 70,80 meters. The piping system
uses HDPE (High Density Polythilene) pipes with a size of 8 inches along 372
meters and 407 meters. At the time of the research the pumping system was not
running continuously due to the high TSS in the settling pond. So there is a
settling pond 1 that formed to settle some of the solid material followed by water
from the recess before entering the settling pond. The maximum TSS value is
3,580 mg / L. The settling pond consists of 1 compartment with a total capacity of
is 1.125 m3 with dredging time every 116 day.
Item Type: | Thesis (Diploma) |
---|---|
Subjek: | T Technology > TD Environmental technology. Sanitary engineering |
Depositing User: | Eny Suparny |
Date Deposited: | 15 Mar 2022 02:26 |
Last Modified: | 15 Mar 2022 08:59 |
URI: | http://eprints.upnyk.ac.id/id/eprint/28949 |
Actions (login required)
![]() |
View Item |