KAJIAN TEKNIS PRODUKTIVITAS ALAT MUAT DAN ALAT ANGKUT UNTUK MENCAPAI TARGET PENGUPASAN OVERBURDEN 165 BCM/JAM DI PIT LEKUKAM PT. TRUBA BARA BANYU ENIM (PT. TBBE) PROVINSI SUMATERA SELATAN

FITRAH, MUHAMMAD (2014) KAJIAN TEKNIS PRODUKTIVITAS ALAT MUAT DAN ALAT ANGKUT UNTUK MENCAPAI TARGET PENGUPASAN OVERBURDEN 165 BCM/JAM DI PIT LEKUKAM PT. TRUBA BARA BANYU ENIM (PT. TBBE) PROVINSI SUMATERA SELATAN. Other thesis, UPN "Veteran" Yogyakarta.

[thumbnail of RINGKASAN.pdf]
Preview
Text
RINGKASAN.pdf

Download (100kB) | Preview

Abstract

RINGKASAN
PT. Truba Bara Banyu Enim (TBBE) merupakan perusahaan
pertambangan batubara, terletak di Kecamatan Gunung Megang, Kabupaten
Muara Enim, Provinsi Sumatera Selatan. Tujuan dari penelitian adalah untuk
mengetahui kemampuan produksi alat muat dan alat angkut yang digunakan,
mengetahui dan memperbaiki faktor-faktor yang menyebabkan tidak tercapainya
target produksi overburden, dan mengupayakan alternatif penyelesaiannya,
sehingga target produksi bisa dicapai.
Target produksi overburden pada Pit Lekukam PT. Truba Bara Banyu
Enim untuk kombinasi excavator hydraulic Caterpillar PC 329D dan dump truck
Hino FM 320 PD adalah sebesar 165 BCM/jam. Target produksi batubara yang
harus tercapai satu tahun adalah 240.000 ton/tahun, sedangkan produksi
pengupasan overburden satu tahun adalah 780.000 BCM/tahun. Target produksi
tersebut belum terpenuhi karena masih terdapat hambatan-hambatan yang terjadi.
Produksi saat ini 1 alat muat excavator hydraulic Caterpillar PC 329D sebesar
136,3 BCM/jam dan 3 unit dump truck Hino FM 320 PD sebesar 101,37
BCM/jam. Tingkat kesediaan alat muat excavator hydraulic Caterpillar PC 329D
adalah mechanical availability (MA) sebesar 81,03%, physical availability (PA)
sebesar 82,06%, use of availability (UA) sebesar 93,41%, dan effective utilization
(EU) sebesar 76,65%. Upaya peningkatan produksi dapat dilakukan dengan cara
meningkatkan waktu kerja efektif dengan melakukan perbaikan terhadap
hambatan-hambatan yang terjadi, sehingga terjadi peningkatan pada efisiensi dan
efektifitas penggunaan alat mekanis. Use of availability (UA) alat mekanis
diketahui meningkat menjadi 99,47%, physical availability (PA) meningkat
menjadi 82,06%, mechanical availabity (MA) meningkat menjadi 81,98%, dan
effective utility (EU) meningkat menjadi 81,63%. Perbaikan waktu kerja
berdampak pada meningkatnya produksi alat mekanis. Produksi alat muat
meningkat menjadi 148,9 BCM/jam dan produksi alat angkut meningkat menjadi
107,9 BCM/jam, tetapi produksi pada alat muat dan alat angkut tersebut belum
dapat memenuhi target produksi yang direncanakan, sehingga dilakukan
penambahan waktu kerja dari 377,6 menit menjadi 566,6 menit. Sehingga
produksi alat muat menjadi 167,9 BCM/jam, sedangkan alat angkut menjadi
121,44 BCM/jam, namun produksi alat angkut belum mencapai target produksi,
sehingga dilakukan penambahan alat, yang semula berjumlah 3 unit menjadi 4
unit. Penambahan 1 unit alat angkut membuat produksi meningkat menjadi 164,9
BCM/jam, sehingga target produksi pengupasan overburden sudah terpenuhi.
Untuk mencapai sasaran produksi sebaiknya perlu adanya penerapan
sistem disiplin kerja bagi operator yang melanggar peraturan, sehingga waktu
kerja efektif dapat berjalan seperti yang diharapkan, serta adanya pemeliharaan
berkala terhadap alat-alat yang digunakan, sehingga kerusakan pada alat dapat
dikurangi.
v
ABSTRACT
PT. Truba Bara Banyu Enim (TBBE) is a coal mining companes, located
in Districts of Gunung Megang, District of Muara Enim, Province of South
Sumatera. This research aims to observe the production capacity of the used
loading and hauling equipment, to investigate and repair the factors lead to not
achieved the overburden production target, and to seek an alternative for its
settlement, so the production target can be achieved.
The overburden production target at Pit Lekukam PT. Truba Bara Banyu
Enim for combination excavator hydraulic Caterpillar PC 329D and dump truck
Hino FM 320 PD is 165 BCM/hour. Coal production targets that must be reached
one year is 240.000 tons/year, while the stripping of overburden a year production
is 780.000 BCM/year. The production target has not fulfilled since there is still
many barriers. Nowadays the production of 1 unit of excavator hydraulic
Caterpillar PC 329D is 136,3 BCM/hour and 3 units of dump truck Hino FM 320
PD is 101,37 BCM/hour. The availability level of excavator hydraulic Caterpillar
PC 329D were mechanical availability (MA) in amount of 81,03%, physical
availability (PA) of 82,06%, use of availability (UA) of 93,41%, and effective
utilization (EU) of 76,65%. The effort to increase production can be conducted by
increasing an effective working time with improving to the barriers, therefore the
increase occurs at the efficiency and effectiveness of mechanical equipment
usage. The use of availability (UA) in mechanical equipment was known increase
into 99,47%, physical availability (PA) increase into 82,06%, mechanical
availabity (MA) increase into 81,98%, and effective utility (EU) increase into
81,63%. The working time improvement has effected to the increase of
mechanical equipment production. The loading equipment production increase
into 148,9 BCM/hour and hauling equipment production increase into 107,9
BCM/hour, but production in the loading equipment and hauling equipment has
not fulfilled a scheduled production target, so that being conducted an addition
times working amount of 377,6 minute becomes 566,6 minute. So the loading
equipment production into 167,9 BCM/hour, while hauling equipment into 121,44
BCM/hour, but production in the hauling equipment has not fulfilled a scheduled
production target, so that being conducted an addition equipment, the original
amounted to 3 units to 4 units. Addition on 1 unit made production of hauling
equipment can increase into 164,9 BCM/hour, so the production target of
overburden removal has been fulfilled.
To reach production goals it is necessary the presence of implementation
the working discipline system for operator who transgress the regulation, so that
an effective working time can work as expected, and the presence of periodical
maintenance to the equipment used, thus the damage in equipment can be
minimized.

Item Type: Thesis (Other)
Subjek: T Technology > TN Mining engineering. Metallurgy
Divisions: x. Faculty of Engineering, Science and Mathematics > School of Engineering Sciences
Depositing User: Ratna Sufiatin
Date Deposited: 24 May 2016 01:42
Last Modified: 24 May 2016 01:42
URI: http://eprints.upnyk.ac.id/id/eprint/2096