KAJIAN TEKNIS PRODUKSI ALAT MUAT DAN ALAT ANGKUT UNTUK MEMENUHI TARGET PRODUKSI BIJIH BESI SEBESAR 150.000 TON/BULAN PADA PT. KOTABESI IRON MINING KOTAWARINGIN TIMUR KALIMANTAN TENGAH

RAHARJO, INDRA (2013) KAJIAN TEKNIS PRODUKSI ALAT MUAT DAN ALAT ANGKUT UNTUK MEMENUHI TARGET PRODUKSI BIJIH BESI SEBESAR 150.000 TON/BULAN PADA PT. KOTABESI IRON MINING KOTAWARINGIN TIMUR KALIMANTAN TENGAH. Masters thesis, UPN "VETERAN" YOGYAKARTA.

[thumbnail of Abstract.pdf]
Preview
Text
Abstract.pdf

Download (14kB) | Preview

Abstract

PT. Kotabesi Iron Mining adalah suatu perusahaan yang bergerak pada
kegiatan penambangan bijih besi di desa Kenyala, kecamatan Telawang, kabupaten
Kotawaringin Timur, provinsi Kalimantan Tengah. Target produksi perusahaan
150.000 ton/bulan dan memiliki 1 alat gali–muat dan 15 alat angkut.
Berdasarkan kenyataan di lapangan masih terjadi ketidakserasian kerja
antara alat gali muat dan alat angkut sehingga produktivitas nyata dari alat-alat
mekanis yang bekerja tidak sesuai dengan target produksi yang direncanakan.
Produksi yang tercapai adalah 115.871,33 ton/bulan.
Tujuan penelitian disini adalah untuk mengetahui keserasian kerja alat muat
dan alat angkut serta untuk mengetahui kemampuan berproduksi dengan
menggunakan 1 unit backhoe dan 15 unit dump truck dalam mencapai target
produksi bijih besi sebesar 150.000 ton/bulan.
Dalam penelitian ini penulis hanya meninjau kegiatan penambangan
dimana alat muat yang bekerja adalah 1 unit Excavator Backhoe CAT 325 D dengan
15 alat angkut Hino FM 260. Produksi alat muat adalah 209.398,8 ton/bulan dan
produkai alat angkut adalah 132.309,3 ton/bulan. Pengkajian terhadap penyebab
tidak tercapainya sasaran produksi oleh alat mekanis ini dititikberatkan pada
peningkatan kinerja alat angkut saja, meliputi waktu kerja efektif, efisiensi kerja dan
keserasian kerja alat yang terjadi pada saat ini.
Upaya pencapaian sasaran produksi dilakukan dengan meningkatkan waktu
kerja efektif alat angkut dari 10,15 jam/hari menjadi 11,51 jam/hari. Meningkatnya
waktu kerja efektif alat angkut maka meningkat juga efisiensi kerja alat angkut dari
78 % menjadi 88,58 %. Peningkatan yang dilakukan mencapai target produksi yaitu
150.255,9 ton/bulan.
Keserasian kerja alat dengan menggunakan 1 unit alat gali muat Exavator
CAT 325 D dan 15 unit alat angkut dump truck HINO FM 260 JD adalah sebesar
0,63 dengan waktu tunggu untuk alat gali muat 0,83 men

PT. Kotabesi Iron Mining is a company engaged in the mining of iron
ore in the village Kenyala, Telawang district, East Kotawaringin district, Central
Kalimantan province. Target production company 150.000 tons/month and has a 1
excavator loading and transportation equipment 15.
Based on the reality on the ground is still going clash between the
working excavator loading and transportation means that the real productivity of
mechanical devices that work not in accordance with the planned production
targets. Production is reached 115.871,33 tons/month.
The research objective here is to determine the compatibility of work
loading tools and transport equipment as well as to determine the production
capacity of using 1 unit backhoe and dump truck 15 units in iron ore production
target of 150.000 tons/month.
In this study the authors simply review the mining activities which fit the
tool works is 1 unit Backhoe Excavator CAT 325 D with 15 conveyances Hino
FM 260. Production equipment is fit 209.398,8 tons/month and production
conveyance was 132.309,3 tons/month. Assessment of the cause of failure to
achieve production targets by a mechanical device is focused on improving the
performance of conveyance only, includes effective work time, work efficiency
and compatibility tools work happening at the moment.
Efforts to achieve the target production is done by increasing the
effective working time conveyance of 10,15 hours/day to 11,51 hours/day.
Increased working time effective conveyance then increased work efficiency also
conveyance of 78 % to 88,58 %. Increase the production target was reached
150.255,9 tons/month.
Compatibility tools work by using 1 unit of loading Exavator CAT 325
D and 15 units of dump truck conveyance HINO FM 260 JD is at 0,63 with the
waiting time for loading excavator 0,83 minutes.

Item Type: Thesis (Masters)
Subjek: T Technology > TN Mining engineering. Metallurgy
Divisions: x. Faculty of Engineering, Science and Mathematics > School of Engineering Sciences
Depositing User: Bugel Suryanta
Date Deposited: 23 May 2016 03:16
Last Modified: 23 May 2016 03:16
URI: http://eprints.upnyk.ac.id/id/eprint/2045