ANALISIS SISTEM KERJA ALAT MUAT DAN ALAT ANGKUT PADA PENAMBANGAN PASIR BATU DI KALI GENDOL KEC. CANGKRINGAN KAB. SLEMAN DAERAH ISTIMEWA YOGYAKARTA

SAMUEL TUMALANG, ISSER (2016) ANALISIS SISTEM KERJA ALAT MUAT DAN ALAT ANGKUT PADA PENAMBANGAN PASIR BATU DI KALI GENDOL KEC. CANGKRINGAN KAB. SLEMAN DAERAH ISTIMEWA YOGYAKARTA. Other thesis, UPN "Veteran" Yogyakarta.

[thumbnail of 2. Cover.pdf]
Preview
Text
2. Cover.pdf

Download (314kB) | Preview
[thumbnail of 3. Abstract.pdf]
Preview
Text
3. Abstract.pdf

Download (95kB) | Preview
[thumbnail of 4. Lembar Pengesahan.pdf]
Preview
Text
4. Lembar Pengesahan.pdf

Download (319kB) | Preview
[thumbnail of 5. DAFTAR ISI .pdf]
Preview
Text
5. DAFTAR ISI .pdf

Download (108kB) | Preview

Abstract

PT. Tri Buana Eka Karsa (Tbek) merupakan perusahaan yang bergerak dalam penyedia jasa alat gali muat yang berlokasi di Kecamatan Cangkringan,
Kabupaten Sleman, Daerah Istimewa Yogyakarta. Lokasi penelitian berada di kuari X dan stockpile. Sistem penambangan yang diterapkan adalah sistem
tambang terbuka. Produksi pasirbatu sebesar 2279,29 ton/hari didapat setelah menentukan jarak dari loading point ke Stockpile. Kegiatan penambangan yang dilakukan adalah penggaruan dan penggalian
pasirbatu, yang sebenarnya telah terdepositkan oleh hasil erupsi gunung Merapi
dengan Backhoe, pemuatan, pengangkutan menuju stockpile dan melewati jalan desa yang menuntut kecepatan yang minim.Pada kenyataan di lapangan, proses kegiatan pemuatan dan pengangkutan
material menggunakan alat mekanis 1 unit backhoe Kobelco SK 200 yang melayani sekitar 30 unit dump truck dengan tipe beberapa dumptruck seperti
dumptruck Hino Dutro 130 HD, Isuzu Elf NKR 71 HD, Colt Diesel HD 120 PS maupun Toyota Dina 130 PS untuk langsung melakukan penjualan material ke
daerah-daerah dan kota-kota terdekat. Permasalahan yang terjadi adalah belum terdapat stockpile agar alat angkut memiliki waktu edar, sehingga tidak memiliki
produksi yang bisa dihitung. Dengan maksud memperoleh waktu edar alat angkut, maka kemudian membuat rekayasa stockpile dengan jarak 5 km dan menghitung
dengan mengambil sampel 1 unit alat gali-muat dan 2 buah alat angkut sebagai acuan menghitung produksi. Kemampuan produksi aktual di lapangan adalah
2120,77 ton/hari dapat ditingkatkan dari menekan waktu kerja yang terbuang karena adanya hambatan kerja baik hambatan yang dapat maupun hambatan yang
tidak dapat ditekan. Upaya peningkatan produksi dapat dilakukan dengan cara meningkatkan
waktu kerja efektif, dan penambahan unit alat gali-muat dan alat angkut. Peningkatan waktu kerja efektif menyebabkan produksi meningkat dari
2120,77 ton/hari menjadi 2279,49 ton/hari. Dalam usaha memaksimalkan agar mendapat produksi yang lebih besar, maka PT. Tbek perlu menetapkan sasaran
produksi 5000 ton/hari guna sebagai acuan untuk melakukan penambahan 2 unit alat angkut dump truck 8-9 ton 1 unit alat gali-muat yaitu backhoe dengan
kapasitas lebih besar.Faktor keserasian kerja adalah 0,318 untuk kuari X kali Gendol
menggunakan 2 unit alat angkut pada waktu kegiatan kerja di kuari X menghasilkan produksi dari 2120,77 menjadi 2279,49 ton/hari. Dalam upaya
mencapai sasaran produksi sebaiknya dilakukan pengawasan terhadap waktu kerja yang telah ditetapkan guna mencegah hambatan-hambatan yang terjadi selama
bekerja.
Kata kunci: pemuatan, pengangkutan, rekayasa stockpile, produksi, efisiensi kerja.

PT. Tri Buana Eka Karsa (Tbek) is a company engaged in service of
digging tools and unloading located in Cangkringan, Sleman, Yogyakarta. The
research location is in quarry X and stockpile. Mining system that is applied is a
system of open-pit mining. Sandstone production for quarry X, amounting to
2279.29 tons / day.
Mining activities are carried out is rip and excavation sandstone, which
had been deposited by the eruption of Mount Merapi with a backhoe, loading,
transportation to the stockpile and pass through the village road that requires
minimal speed.
In the circumstances, the process of loading and transportation of materials
using mechanical means 1 unit backhoe Kobelco SK 200 that serves
approximately 30 units of dump trucks with type multiple dumptruck like
dumptruck Hino Dutro 130 HD, Isuzu Elf NKR 71 HD, Colt Diesel HD 120 PS
and Toyota Dina 130 PS to direct selling material to the affected areas and nearby
towns. The problem that occurs is not yet there is a stockpile that conveyance has
a circulation time, so it has no production can be calculated. With a view to
obtaining a circulation conveyance, then later made engineering stockpiles with a
distance of 5 km and counting by sampling 1 excavating-loading unit and two
pieces of conveyance as the reference counting production. The actual production
capability in the field 2120.77 tons / day can be increased from the pressing work
time is wasted because of constraints that can work both barriers and c onstraints
that can not be suppressed. The existence of these barriers will reduce the
effective working time, causing low work efficiency.
Efforts to improve production can be done by increasing the effective
working time, and the addition of excavating-loading unit and conveyances. The
increase in the effective working time led to increased production
of 2120.77 tons/day to 2279.49 tons/day. In an effort to maximize in order to get
greater production, then the PT. Tbek need to set a production target of 5000 tons
/ day to as a reference for the addition of 2 units of conveyances 8-9 ton dump
truck 1 excavating-loading unit that backhoe with greater capacity of 1.8 m3.
Factors harmony tools work becomes 0.318 for quarry X Gendol river
using two units of conveyance at the time working in quarry X result in the
production of 2279.49 tons/day becomes 2120.77 tons/day. In order to achieve
the production target should be conducted surveillance of working time that has
been set in order to avoid the obstacles that occur during the work.
Keywords: loading, transportation, stockpile engineering, production, working
efficiency.

Item Type: Thesis (Other)
Subjek: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: x. Faculty of Engineering, Science and Mathematics > School of Engineering Sciences
Depositing User: Eko Yuli
Date Deposited: 09 Sep 2016 06:56
Last Modified: 09 Sep 2016 06:56
URI: http://eprints.upnyk.ac.id/id/eprint/6143

Actions (login required)

View Item View Item