KAJIAN TEKNIS PRODUKSI ALAT MUAT DAN ALAT ANGKUT UNTUK MEMENUHI KEGIATAN PRODUKSI BATUBARA DI PT. TANTRA COALINDO INTERNATIONAL KABUPATEN PERANAP, RIAU

NAUFALDY, HARSYA (2019) KAJIAN TEKNIS PRODUKSI ALAT MUAT DAN ALAT ANGKUT UNTUK MEMENUHI KEGIATAN PRODUKSI BATUBARA DI PT. TANTRA COALINDO INTERNATIONAL KABUPATEN PERANAP, RIAU. Other thesis, Universitas Pembangunan Nasional Veteran Yogyakarta.

[thumbnail of Cover.pdf]
Preview
Text
Cover.pdf

Download (54kB) | Preview
[thumbnail of Lembar Pengesahan.pdf]
Preview
Text
Lembar Pengesahan.pdf

Download (166kB) | Preview
[thumbnail of Daftar Isi.pdf]
Preview
Text
Daftar Isi.pdf

Download (23kB) | Preview
[thumbnail of Abstract dan ringkasan.pdf]
Preview
Text
Abstract dan ringkasan.pdf

Download (14kB) | Preview

Abstract

Produksi Batubara saat ini masih belum cukup untuk memenuhi
kebutuhan batubara pada stockyard. Target produksi batubara yang dimiliki PT.
Tantra Coalindo International, sebesar 25.277ton/bulan. Pembongkaran Batubara
dilakukan dengan pengupasan lapisan tanah penutup, dimana material hasil
pengupasan dimuat dan diangkut menuju stockyard. Kegiatan pengangkutan
Batubara menggunakan dump truck Hino 260 JD. Total produksi alat muat dengan
jumlah satu unit saat ini sebesar 33.575 ton/bulan dan produksi alat angkut dengan
jumlah 3 unit sebesar 21.823 ton/bulan.
PT. Tantra Coalindo International, ingin memenuhi kebutuhan batubara
sebesar 25.277 ton/bulan, sehingga untuk memenuhi kebutuhan yang diinginkan
tersebut maka perlu diketahui seberapa banyak alat mekanis yang digunakan
untuk memenuhi kebutuhan produksi tersebut.
Dari hasil penelitian di lapangan dari rangkaian-rangkaian yang
mempengaruhi produksi di lapangan, produksi dapat ditingkatkan dengan
melakukan perbaikan waktu kerja efektif yang digunakan. Efisiensi kerja saat ini,
yaitu 66,10 % pada excavator Komatsu PC 300, dan 57,33 % pada dump truck
Hino 260 JD. Dengan melakukan perbaikan waktu kerja dan pemilihan waktu
yang sesuai dengan target produksi, maka efisiensi kerja alat mekanis menjadi
70,46 % pada Excavator Komatsu PC 300, dan 61,78 % pada dump truck Hino
260 JD. Dengan pemilihan yang tepat pada efisiensi kerja alat mekanis, Produksi
alat muat menjadi 33.575 ton/bulan dan produksi alat angkut sebesar 21.823
ton/bulan.
Meskipun melakukan pemilihan waktu kerja yang sesuai, namun waktu
kerja alat mekanis produksi alat angkut belum mencukupi untuk memenuhi target
produksi batubara sebesar 25.277 ton/bulan, sehingga perlu adanya peningkatan
waktu kerja efektif. Produksi alat angkut meningkat dengan adanya peningkatan
waktu kerja efektif. Produksi alat angkut meningkat menjadi 26.821 ton/bulan
menggunakan peningkatan waktu kerja efektif dan produksi alat muat 38.204
ton/bulan menggunakan peningkatan waktu kerja efektif. Dengan demikian target
produksi sebesar 25.277 ton/bulan dapat terpenuhi.
v
ABSTRACT
Coal production is currently not enough to meet coal needs in the
stockyard. The coal production target owned by PT. Tantra Coalindo
International, amounting to 25,277 tons / month. Coal dismantling is carried out
by stripping the overburden, where the stripping material is loaded and
transported to the stockyard. Coal transportation activities use Hino 260 JD dump
trucks. The total production of loading equipment with the current number of one
unit is 33,575 tons / month and the production of transportation equipment is 3
units of 21,823 tons / month.
PT. Tantra Coalindo International, wants to fulfill coal needs of 25,277
tons / month, so that to meet the desired needs, it is necessary to know how many
mechanical devices are used to meet these production needs.
From the results of research in the field of circuits that affect production
in the field, production can be increased by making improvements to the effective
working time used. Current work efficiency, namely 66.10 % on Komatsu PC 300
excavators, and 57.33 % on Hino 260 JD dump trucks. By making improvements
to working time and the selection of time according to the production target, the
working efficiency of mechanical devices became 70.46 % in the PC 300 Komatsu
Excavator, and 61.78 % in the 260 JD Hino dump truck. With the right selection
on the working efficiency of mechanical devices, the production of loading
equipment becomes 33,575 tons / month and the production of conveyance
increases to 21,823 tons / month.
Even though the selection of working time is appropriate, the working time
of the mechanical means of transporting the equipment is not sufficient to meet the
increasing coal demand of 25,277 tons / month, so that the duration of working
hours is needed. Production of transportation equipment increases with the
addition of working hours. Production of conveyance increased to 26,821 tons /
month using the lowest time alternative and the production of loading equipment
38,204 tons / month using the lowest time alternative. Thus the production target
of 25,277 tons / month can be fulfilled.

Item Type: Thesis (Other)
Subjek: T Technology > T Technology (General)
Divisions: x. Faculty of Engineering, Science and Mathematics > School of Engineering Sciences
Depositing User: Sarimin Sarimin
Date Deposited: 14 Aug 2019 08:06
Last Modified: 14 Aug 2019 08:06
URI: http://eprints.upnyk.ac.id/id/eprint/20742

Actions (login required)

View Item View Item