KAJIAN SISTEM PENYALIRAN TAMBANG PADA LOKASI PENAMBANGAN BATUBARA PIT 8 PT PIPIT MUTIARA JAYA SITE BEBATU KECAMATAN SESAYAP ILIR KABUPATEN TANAH TIDUNG PROVINSI KALIMANTAN UTARA

ADRIANSYAH S, ADRIANSYAH S (2016) KAJIAN SISTEM PENYALIRAN TAMBANG PADA LOKASI PENAMBANGAN BATUBARA PIT 8 PT PIPIT MUTIARA JAYA SITE BEBATU KECAMATAN SESAYAP ILIR KABUPATEN TANAH TIDUNG PROVINSI KALIMANTAN UTARA. Other thesis, UPN 'VETERAN" YOGYAKARTA.

[thumbnail of ABSTRAK.pdf]
Preview
Text
ABSTRAK.pdf

Download (272kB) | Preview

Abstract

Pit 8 merupakan proyek penambangan batubara milik PT. Pipit Mutiara
Jaya yang berlokasi di Kecamatan Sesayap, Kabupaten Tana Tidung, Provinsi
Kalimantan Utara dengan menggunakan sistem tambang terbuka. Pada kegiatan
tambang terbuka, curah hujan yang tinggi akan berpotensi mengganggu operasi
penambangan. Untuk mengatasi masalah tersebut, diperlukan sistem penyaliran
tambang yang baik.
Kajian teknis sistem penyaliran tambang PT. Pipit dimulai dengan analisis
data curah hujan, perhitungan debit rencana, mengkaji dimensi saluran terbuka,
volume sumuran (sump), penentuan lama waktu pemompaan untuk mengeringkan
lokasi penambangan yang tergenang air serta melakukan penjadwalan waktu
pengerukan kolam pengendapan.
Berdasarkan analisis data curah hujan tahun 2004 – 2013 diperoleh curah
hujan rencana harian sebesar 137,24 mm, intensitas curah hujan 47,58 mm/jam
dengan periode ulang hujan 3 tahun dan resiko hidrologi sebesar 86,83 %. Daerah
tangkapan hujan pada lokasi penelitian memiliki luas 0,76 km
2
dengan debit air
limpasan 5,99 m
3
/detik.
Berdasarkan hasil perhitungan dimensi saluran terbuka aktual telah
mencukupi untuk mengalirkan air yang berasal dari debit pemompaan yaitu
sebesar 380 m
3
/jam pada sumuran, 420 m
3
/jam pada genangan air. Kebutuhan
volume sumuran sebesar 62.593 m
3
dengan 1 (satu) pompa dan 54.101 m
3
pada
sumuran dengan 2 (dua) pompa sedangkan volume sumuran yang tersedia secara
aktual yaitu 45.663 m
3
sehingga perlu di lakukan penambahan dimensi volume
sumuran. Hasil perhitungan lama waktu pemompaan pada lokasi genangan air
yaitu selama 17 hari. Faktor-faktor yang berpengaruh dalam perhitungan lama
waktu pemompaan yaitu curah hujan, lama waktu hujan, volume air awal pada
lokasi genangan air, performa dan kapasitas pemompaan. Berdasarkan hasil
perhitungan kolam pengendapan harus dilakukan perawatan pengerukan pada
kompartemen pertama dengan luas 334,56 m
2
dan volume 176,64 m
3
dilakukan
setiap 61 hari sekali, kompartemen dua dengan luas 306 m² dan volume 225,6 m
3
setiap 78 hari sekali, serta kompartemen ketiga yang memiliki luas 416,25 m
2
dan
volume 196,8 m
3
setiap 68 hari sekali.

Pit 8 is a coal mining project, owned by PT. Pipit Mutiara Jaya, is
located in Sesayap District, Tana Tidung , North Kalimantan Province with using
the open mine system. In the open-pit mining activities, heavy rainfall will
potentially disrupt mining operations. To overcome these problems, it needs a
good system of mines drainage.
Technical review drainage system PT. Pipit begins with an analysis of
rainfall data, the calculation of the discharge plan, assess the dimensions of the
open channel, volume wells (sump), determining the length of time pumping to
drain the flooded mine site as well as the scheduling o f time dredging the settling
ponds.
Based on the analysis of rainfall data of 2004 - 2013 obtained rainfall
daily plan amounted to 137.24 mm , 47.58 mm rainfall intensity/hr with a 3-year
return period rainfall and hydrology risk by 86.83 %. Catchment at the study site
has an area of 0.76 km
2
with runoff water discharge 5.99 m
3
/s.
Based on the results of the calculation of the actual dimensions of open
channels was sufficient to drain water from the pumping discharge is 380 m
3
/hr
on wells, 420 m
3
/h at a puddle. The needs of sump volume is 62,593 m
3
with
1(one) pump and 54,101 m
3
in sump with 2 (two) pumps while available volume
actually is 45,663 m
3
so the need to do additional dimension of sump volume.
Results of a calculation the time to pumping the puddle in location is 17 days.
The factors that influence the calculation of the length of time pumping are
rainfall, duration of rain, the initial water volume at the location of a puddle,
performance and capacity of pumping. Based on the results of the calculation of
settling ponds should be carried out maintenance dredging on the first
compartment with an area of 334.56 m
2
and a volume of 176.64 m
3
every 61 days,
the second compartment with an area of 306 m
2
and a volume of 225.6 m
3
every
78 days and the third compartment wide 416.25 m
2
and a volume of 196.8 m
3
every 68 days.

Item Type: Thesis (Other)
Subjek: T Technology > TN Mining engineering. Metallurgy
Divisions: x. Faculty of Engineering, Science and Mathematics > School of Engineering Sciences
Depositing User: Darsini Darsini
Date Deposited: 16 May 2016 03:11
Last Modified: 16 May 2016 03:11
URI: http://eprints.upnyk.ac.id/id/eprint/945

Actions (login required)

View Item View Item