PENINGKATAN PRODUKTIVITAS ALAT BOR PADA KUARI BATUGAMPING DI PT. INDOCEMENT TUNGGAL PRAKARSA Tbk PALIMANAN CIREBON JAWA BARAT

SUBAKTI ANWAR, FARID (2014) PENINGKATAN PRODUKTIVITAS ALAT BOR PADA KUARI BATUGAMPING DI PT. INDOCEMENT TUNGGAL PRAKARSA Tbk PALIMANAN CIREBON JAWA BARAT. Other thesis, UPN ''VETERAN'' YOGYAKARTA.

[thumbnail of ABSTRACT - FARID SUBAKTI ANWAR - 112060068.pdf]
Preview
Text
ABSTRACT - FARID SUBAKTI ANWAR - 112060068.pdf

Download (15kB) | Preview

Abstract

Penambangan batugamping yang dilakukan PT. Indocement Tunggal Prakarsa
Tbk terletak di Desa Palimanan Barat, Kecamatan Gempol, Kabupaten Cirebon,
Provinsi Jawa Barat. Kegiatan penambangan yang telah dilakukan meliputi:
pembabatan, pengupasan tanah penutup, pembongkaran, pemuatan dan
pengangkutan. Proses pembongkaran batugamping menggunakan metode
pengeboran dan peledakan.
Salah satu faktor yang mempengaruhi kelancaran operasi peledakan antara
lain tergantung pada kegiatan pengeboran. Pada kenyataan di lapangan produksi
alat-alat bor di PT. ITP Tbk Palimanan Cirebon masih belum sesuai harapan, ini
bisa dilihat dari produksi pengeboran batugamping nyata sebelum perbaikan dari
alat-alat bor yang digunakan pada kuari penambangan batugamping PT. ITP Tbk
Palimanan Cirebon adalah sebesar 2.057.323,09 Ton/tahun. Angka produksi
pengeboran tersebut lebih kecil target produksi batugamping untuk klinker yaitu
sebesar 3.366.469 Ton/tahun.
Oleh karena itu, perlu diadakan peningkatan produktivitas alat-alat bor guna
mencapai target produksi. Faktor-faktor yang mempengaruhi proses pengeboran
dan berpengaruh terhadap produksi pengeboran antara lain adalah laju
pengeboran, efisiensi waktu pengeboran, waktu kerja efektif, keahlian operator
alat bor serta jarak spacing dan burden.
Peningkatan waktu kerja efektif yang dilakukan dalam upaya meningkatkan
produksi pengeboran adalah dengan cara menekan hambatan-hambatan yang
masih dapat dihindari. Penambahan jarak spacing dan burden perlu dilakukan
dengan tujuan supaya volume setara yang dihasilkan dapat lebih besar sehingga
produksi pengeboran meningkat dan target produksi tercapai.
Produksi pengeboran yang dihasilkan dengan upaya peningkatan adalah
sebagai berikut:
1. Peningkatan waktu kerja efektif, yaitu mengurangi waktu hambatan yang
dapat dihindari, maka dihasilkan produksi sebesar 3.045.389,137
Ton/tahun.
2. Peningkatan waktu kerja efektif dan penambahan jarak spacing dan
burden, maka dihasilkan produksi sebesar 4.138.770,02 Ton/tahun yang
memenuhi target produksi.
kata kunci : produktivitas, pengeboran, peledakan.

Limestone mining by PT. Indocement Tunggal Prakarsa Tbk Palimanan
Cirebon West Java located in Palimanan Barat Village, District Gempol, Cirebon,
West Java Province. Mining activities that have been done include: clearing,
overburden stripping, dismantling, loading and transporting. Limestone unloading
process using drilling and blasting method.
One factors that affect maximum operation of blasting, among others is
depending on drilling activity. In the reality drilling machines production in PT.
ITP Tbk Palimanan Cirebon still does not meet expectations, it can be seen from
the real drilling production of drilling machines used in mining limestone
quarrying PT. ITP Tbk palimanan Cirebon before repairing. Drilling production
amounted to 2,057,323.09 tons / year. Drilling production is smaller than
limestone production target for clinker that equal to 3,366,469 tons / year.
Therefore, there should be increasing the productivity of drilling machines
to achieve production targets. Factors affecting the drilling process and affect the
production rate of drilling are drilling rate, drilling time efficiency, effective
working time, operator skills and distance carrier spacing and burden.
Increasing the effective working time in an attempt to increase production by
drilling are lowering barriers that still can be avoided. Imcreasing spacing and
burden distance needs to be done for the goal of equal volume produced. It can be
larger, so the drilling production increased and production targets achieved.
There are the result of increasing drilling production:
1. Increasing effective working time, which reduces the time constraints that
can be avoided, then the resulting production is 3,045,389.137 tons / year.
2. Increasing effective working time and increasing spacing and burden
distance, then the result production is 4,138,770.02 tons / year. Meet
production targets.
Keywords: Productivity, Drilling, Basting

Item Type: Thesis (Other)
Subjek: T Technology > TN Mining engineering. Metallurgy
Divisions: x. Faculty of Engineering, Science and Mathematics > School of Engineering Sciences
Depositing User: Erny Azyanti
Date Deposited: 09 Nov 2016 08:59
Last Modified: 09 Nov 2016 08:59
URI: http://eprints.upnyk.ac.id/id/eprint/8626

Actions (login required)

View Item View Item