EVALUASI PENERAPANGROUND CONTROLMANAGEMENT PLANPADA TAMBANG BAWAH TANAH KENCANA PT. NUSA HALMAHERA MINERALS

TAMPUBOLON, ERWIN (2015) EVALUASI PENERAPANGROUND CONTROLMANAGEMENT PLANPADA TAMBANG BAWAH TANAH KENCANA PT. NUSA HALMAHERA MINERALS. Masters thesis, UPN ''VETERAN'' YOGYAKARTA.

[thumbnail of 03. ABSTRACT.pdf]
Preview
Text
03. ABSTRACT.pdf

Download (75kB) | Preview
[thumbnail of 04. RINGKASAN.pdf]
Preview
Text
04. RINGKASAN.pdf

Download (88kB) | Preview

Abstract

Perusahaan tambang wajib mempunyai rencana pengelolaan kontrol batuan,
apakah itu tambang terbuka atau tambang bawah tanah. Tambang bawah tanah
Kencana dimiliki oleh PT. Nusa Halmahera Minerals menyadari kebutuhan dan
manfaat ini dan telah menggunakannya sejak tahun 2005.
Permasalahan yang terjadi adalah massa batuan yang lemah dan berdampak
pada waktu siklus penambangan. Dengan permasalahan yang ada, kemajuan
rencana penambangan, kebutuhan produksi termasuk nilai cut-off grade telah
mengakibatkan pentingnya melakukan evaluasi aplikasi GCMP (Ground Control
Management Plan). GCMP terdiri dari petunjuk dan persyaratan sistem
penyangga, analisa resiko dan kestabilan penggalian, dll. Tujuan dari penelitian
ini adalah mengevaluasi aplikasi GCMP dan melihat peluang untuk meningkatkan
kinerja produksi lebih baik lagi dengan menghasilkan waktu siklus penambangan
lebih rendah dengan aman, tanpa berkompromi pada keselamatan kerja. Hal ini
akan merupakan benefit jangka panjang kestabilan tambang.
Dua hal yang dievaluasi terjadi pada batuan tipe 3 dan 4, dan berfokus
mengurangi ketebalan beton tembak di batuan tipe 3 dan menggabungkan dua
fase penyemprotan beton tembak masing-masing ketebalan 50 mm pada tiap
lapisan menjadi satu fase penyemprotan dengan ketebalan beton tembak 100 mm.
Metodologi penelitian mencakup ulasan mix design, pengumpulan data siklus
penambangan dan kekuatan awal beton tembak.
Berdasarkan hasil yang didapat, perbaikan signifikan siklus penambangan
terjadi pada kedua tipe batuan dengan menghasilkan 28 % dan 29 % lebih cepat
siklus penambangannya dibandingkan dengan sebelum dilakukan evaluasi, secara
konsisten mencapai kekuatan awal 1 MPa dalam 60 menit.
Hasil yang baik ini perlu untuk dijaga dan dievaluasi secara berkala dan
penting untuk mengawasi standar dan aplikasi sistem penyanggaan dengan
penerapan GCMP secara benar untuk mencapai produksi yang aman. Akan tetapi,
hasil lain dari ulasan ini adalah masih ada peluang untuk mendapatkan
penambangan dengan lebih produktif dengan melakukan tindak lanjut dan
mengurangi waktu menunggu yang teridentifikasi dalam siklus penambangan.

It is a mandatory for a mine company to have a management plan for
ground control either a surface or underground mine. Underground Mine
Kencana owned by PT. Nusa Halmahera Minerals realizes this needs and benefit
and has established this management plan since 2005.
The problem thatoccursis weak rock mass and impacted to cycle time to
mine. With the ongoing issues, the advance of mining plan,physical production
requirement including cut-off grade value have resulted the imperative of
reviewing the application of GCMP (Ground Control Management Plan). GCMP
consists of a ground support guideline, requirement, role and responsibility,
geotechnical condition, data collection, risk assessment and excavation stability,
etc. The purpose of this study is to evaluate the application of GCMP and see any
opportunities to improve production performance better by having shorter mining
cycle time safely, without compromising safety. This will be a benefit for long
term mine stability.
Two points reviewed happened in rock type 3 and 4 and focusing on
reducing shotcrete thickness in rock type 3 and consolidating two passes of
shotcrete spraying with 50 mm thickness each layer in rock type 4 into single pass
shotcrete spraying with 100 mm thickness. Research methodology covers mix
design review, data collection on mining cycle time and shotcrete early strength.
Based on the result obtained, significant cycle time improvement appears to
happened in both rock type by having 28 % and 29 % faster in cycle time compare
to condition before review happened and consistently achieving 60 minutes on
early strength to gain 1 MPa.
This good result need to be maintained and reviewed regularly and it is
important to supervise the ground support standard and application by
implementing GCMP properly to achieve safe production. However, in the result
of this evaluation, there is still opportunity to have more productive work in
mining by follow upand reduce waiting time identified in mining cycle time.

Item Type: Thesis (Masters)
Subjek: T Technology > TN Mining engineering. Metallurgy
Divisions: x. Faculty of Engineering, Science and Mathematics > School of Engineering Sciences
Depositing User: Erny Azyanti
Date Deposited: 03 Nov 2016 03:10
Last Modified: 03 Nov 2016 03:10
URI: http://eprints.upnyk.ac.id/id/eprint/8301

Actions (login required)

View Item View Item