STUDI GEOMETRI PELEDAKAN UNTUK MENCAPAI SASARAN PRODUKSI TANAH PENUTUP DI PIT M CUTBACK BARAT, PT. BUKIT MAKMUR MANDIRI UTAMA JOBSITE KIDECO, BATU KAJANG, KALIMANTAN TIMUR

NABABAN, VICTOR GOODLIFE (2012) STUDI GEOMETRI PELEDAKAN UNTUK MENCAPAI SASARAN PRODUKSI TANAH PENUTUP DI PIT M CUTBACK BARAT, PT. BUKIT MAKMUR MANDIRI UTAMA JOBSITE KIDECO, BATU KAJANG, KALIMANTAN TIMUR. Other thesis, UPN "Veteran" Yogyakarta.

[thumbnail of ABSTRACT.pdf]
Preview
Text
ABSTRACT.pdf

Download (43kB) | Preview

Abstract

ABSTRACT
PT. Bukit Makmur Mandiri Utama (PT.BUMA) is one of the contractors
working on the site owned by PT. Kideco Jaya Agung in East Kalimantan, which
produces coal as an energy source. In PT. BUMA jobsite Kideco, there are three pit
namely pit M, pit A and pit B. Astronomically PT. Bukit Makmur Mandiri Utama is
located at 1 ° 45'-2 ° south latitude and 115 ° 45-116 ° East longitude and the
administration of the coal mining site of PT. Kideco Jaya Agung including Batu
Village area of Kajang, District Batu Sopang, Pasir Regency, East Kalimantan
Province.
The purpose of this study is to find the cause of not achieving the target for
rock fragmentation by blasting results boulder maximum percentage of 15% and
examines the application of current blasting geometry, make improvements in order
to achieve the desired fragmentation while still referring to the company standards.
This is to facilitate further activities such as loading activities, transport and
the achievement of production targets soil movement. Target production stripping
overburden existing in pit M CB West, which is in May 2012 of 23.542 m /blasting
and in June 2012 amounted to 37.648 m3 /blasting. Without boulder blasting volume
in May was 18.258 m3 /blastign resulting in a lack of production of 6,478 m3.
There are two proposed designs blasting geometry where the first proposal
aims to optimize the powder factor and the second proposal maximizes powder
factor where boulder average percentage produced remains below 15%. Experiment
with blasting geometric design done in June, with a production target of 37.648
m3/blasting, without boulder blasting volume of 39.733 m3/blasting.
In the first proposal to burden = 8 m, spacing = 9 m, blast holes depth = 12 m,
stemming = 5.6 m, column length = 6.4 m. The design of the blasting geometry,
resulting in fragmentation sized rocks > 1.5 m which is 10.99% and the powder factor
of 0.26 kg/m3.
In the second proposal to burden = 8 m, spacing = 9 m, blast holes depth = 12
m, stemming = 5 m, the columns length = 7 m. The design of the blasting
geometry,resulting in fragmentation sized rocks > 1.5 m which is 6.04% and the
powder factor of 0.30 kg/m3.

Item Type: Thesis (Other)
Subjek: T Technology > TN Mining engineering. Metallurgy
Divisions: x. Faculty of Engineering, Science and Mathematics > School of Civil Engineering and the Environment
Depositing User: Ratna Sufiatin
Date Deposited: 11 Oct 2016 04:36
Last Modified: 11 Oct 2016 04:36
URI: http://eprints.upnyk.ac.id/id/eprint/7523

Actions (login required)

View Item View Item