FUADI, ANUAR (2013) RENCANA PENATAAN TOP SOIL PADA DISPOSAL PIT S5 BLOK SIAMBUL PT. RIAU BARAHARUM (RBH) DESA SIAMBUL, KECAMATAN BATANGGANSAL, KABUPATEN INDRAGIRI HULU, PROVINSI RIAU. Other thesis, UPN "Veteran" Yogyakarta.
Preview |
Text
RINGKASAN.pdf Download (19kB) | Preview |
Abstract
RINGKASAN
PT. Riau Baraharum (RBH) merupakan perusahaan tambang batubara
yang berlokasi di desa Siambul, Kecamatan Batanggansal, Kabupaten Indragiri
Hulu, Provinsi Riau. Kegiatan penambangan di PT. RBH dilakukan dengan
menggunakan metode tambang terbuka (open pit). Akibat dari kegiatan
penambangan ini maka harus dilakukan kegiatan penataan lahan untuk
mengurangi dampak kerusakan lahan akibat penambangan.
Tujuan dari penelitian ini adalah pengelolaan top soil dengan
membandingkan 3 metode yaitu, metode perataan, metode guludan dan metode
pot/lubang. Serta merekomendasikan metode penataan top soil yang terbaik untuk
diterapkan pada disposal pit S5.
Luas area disposal yang akan dilakukan penataan top soil adalah 35.4 Ha.
Top soil yang tersedia pada Bank soil adalah 207.400 LCM. Oleh karna itu, untuk
menghemat ketersediaan top soil perlu dilakukan pemilihan metode yang tepat.
Serta waktu yang dibutuhkan untuk pengerjaan masing-masing metode, agar
nantinya dapat digunakan untuk perbandingan dan merekomendasikan metode
yang terbaik.
Penerapan penataan top soil akan dibagi menjadi 2 area, yaitu area datar
18,22 Ha dan area miring 17,18 Ha, hal ini disebabkan karena bentuk disposal
yang berjenjang. Hasil perhitungan kebutuhan top soil pada area dengan
menggunakan metode perataan adalah 102.032 LCM, metode guludan adalah
61.152 LCM, metode pot adalah 19.531,84 LCM, dan metode pot pada area
miring adalah 5.016,56 LCM. Waktu pengerjaan pada area datar metode perataan
adalah 7 hari, metode guludan adalah 5 hari, metode pot adalah 9 hari, dan
metode pot pada area miring adalah 3 hari. Alat yang dibutuhkan untuk
pengerjaan metode perataan dan guludan adalah bulldozer tipe D7G2 dan untuk
metode pot menggunakan excavator tipe ZX 210.
Pemindahan top soil dari bank soil ke disposal dikerjakan 6 hari. Hasil
perhitungan top soil dan waktu pengerjaan tersebut, dipilih metode yang terbaik
untuk diterapkan pada disposal pit S5, yaitu metode perataan pada area datar, dan
metode pot pada area miring. Total kebutuhan top soil yang dibutuhkan adalah
107.048,56 LCM dengan waktu pengerjaan 10 hari.
ABSTRACT
PT. Riau Baraharum (RBH) is a coal mining company located in the
village Siambul, District Batanggansal, Indragiri Hulu, Riau Province. Mining
activities at PT. RBH is done using open pit methods (open pit). As a result of the
mining activities should be performed landscaping activities to reduce the impact
of land degradation caused by mining.
The purpose of this study is the management of top soil by comparing 3
perataan methods, guludan methods, and lubang/pot methods. And to recommend
methods of structuring the best top soil to be applied to a disposal pit S5.
Disposal area will be to restructure the top soil is 35.4 Ha. Top soil
available on the Bank's soil is 207 400 LCM. By because it is, to save on the
availability of top soil selection method needs to be done right. As well as the
time required for processing each method, so that later can be used for comparison
and recommend the best method.
Application of top soil arrangement will be divided into two areas, namely
flat sloping area of 18.22 ha and 17.18 ha, this was due to a tiered form of
disposal. The results of calculations need top soil in the area by using the
smoothing method is 102 032 LCM, LCM method mound is 61 152, the method is
19531.84 LCM pot, and pot method on sloping area is 5016.56 LCM. Processing
time on a flat area smoothing method is 7 days, the mounds method is 5 days, 9
days is a pot method, and the method of the pot in the oblique area is 3 days.
Tools needed to work on and mound smoothing method is D7G2 type bulldozers
and excavators to use the pot method type ZX 210.
Removal of top soil bank soil disposal to be done 6 days. Top soil
calculation results and the processing time, selected the best method to apply to
the disposal pit S5, the method of smoothing in flat areas, and methods of pot in
sloping areas. Total needs of top soil needed is 107,048.56 LCM with processing
time 10 days.
Item Type: | Thesis (Other) |
---|---|
Subjek: | T Technology > TN Mining engineering. Metallurgy |
Divisions: | x. Faculty of Engineering, Science and Mathematics > School of Civil Engineering and the Environment |
Depositing User: | Ratna Sufiatin |
Date Deposited: | 11 Oct 2016 02:55 |
Last Modified: | 11 Oct 2016 02:55 |
URI: | http://eprints.upnyk.ac.id/id/eprint/7506 |
Actions (login required)
![]() |
View Item |