RANCANGAN TEKNIS SISTEM PENYALIRAN PIT A TAHUN 2015 PADA TAMBANG BATUBARA DI PT.DARMAHENWA BENGALON COAL PROJECT SITE KPC PROV. KALIMANTAN TIMUR

ADJI, A.A.GEDE CHANDRA (2015) RANCANGAN TEKNIS SISTEM PENYALIRAN PIT A TAHUN 2015 PADA TAMBANG BATUBARA DI PT.DARMAHENWA BENGALON COAL PROJECT SITE KPC PROV. KALIMANTAN TIMUR. Other thesis, UPN "Veteran" Yogyakarta.

[thumbnail of RINGKASAN DAN ABSTRAK.pdf]
Preview
Text
RINGKASAN DAN ABSTRAK.pdf

Download (165kB) | Preview
[thumbnail of SKRIPSI.pdf] Text
SKRIPSI.pdf
Restricted to Repository staff only

Download (14MB)

Abstract

Kegiatan Penambangan Batubara di PT.DarmaHenawa,Tbk menggunakan sistem tambang terbuka dengan metode strip mine. Kemajuan tambang di PT.DarmaHenawa,Tbk menyebabkan sistem penyaliran tambang ikut berubah.
Oleh karena itu perlu adanya rancangan terhadap sistem penyaliran sesuai dengan
kemajuan tambang. Berdasarkan analisis curah hujan yang dilakukan di daerah penelitian,
diperoleh curah hujan rencana 90,88 mm/hari untuk Pit A Utara (Jeruk) dan 106,37 mm/hari untuk di Pit A Selatan (Anggrek) pada periode ulang hujan
10tahun, intensitas hujan sebesar 17,7 mm/jam untuk Pit A Utara (Jeruk) dan 15,1mm/jam untuk PitA Selatan (Anggrek). Lokasi penambangan PT.DarmaHenawa,Tbk dibagi menjadi 4 Daerah Tangkapan Hujan (DTH) dengan
total debit air yang masuk ke dua sumuran sebesar 28,67 m3
/detik (Quarter I ),28,7 m3/detik (QuarterII), 28,7 m3
/detik (Quarter III) dan 30,5m/detik
(QuarterIV). Total debit air yang dapat dialihkan sebesar 5,05 m3/detik (Quarter I– IV). Terdapat 2 rancangan saluran terbuka berbentuk trapesium untuk mencegah
air limpasan tidak masuk ke dalam Pit. Dimensi saluran terbuka dibuat berdasarkan rumus Manning dengan dimensi saluran sebagai berikut:a. Saluran Terbuka I (RL 3) : h ( tinggi saluran ) = 1,5 m; b ( lebar dasar saluran ) = 1,4 m; B ( lebar permukaan ) = 4 m
b. Saluran Terbuka II(Kelawitan ) : h ( tinggi saluran) = 1,2 m; b ( lebar dasar saluran ) = 1,1 m;
B ( lebar permukaan ) = 3 m Volume sumuran dihitung berdasarkan jumlah air yang masuk dan debit
pemompaan. Sumuran Pit A Utara (Jeruk) menggunakan 3 line unit pompa staging (Multiflo MF-420E dan MF 385) untuk Quarter I – III dan sumuran Pit A
Selatan ( Jeruk ) menggunakan 2 line unit pompa staging (Multiflo MF 420E dan MF 385) untuk Quarter I – III dengan debit total 584 m3/jam dan volume sumuran 238.209,8 m3
untuk Pit A Utara ( Jeruk ) dan 112.303,6 m
untuk Pit A Selatan (Anggrek), sedangkan untuk Quarter IV dibutuhkan 5 line unit pompa staging dengan volume sumuran 350.513,4 m.

3
3
3

ABSTRACT
vi

Coal mining activities at PT.DarmaHenawa,Tbk using surface mining
system with strip mine method. Mine sequence made the system of water
management changed. Because of that, evaluation of water management is
needed.
Based on the analysis of rainfall which was done in area of research,
obtained plans 90,88 mm/day of rainfall for Pit A Utara (Jeruk) and
106,37mm/hari at Pit A Selatan (Anggrek) with 10 years return period of rainfall ,
the intensity of rainfall 17,7 mm/hour at Pit A Utara (Jeruk) and 15,1 mm/hour at
Pit A Selatan (Anggrek). The location of mining company is devided into
4regional catchment area of rainfall with total discharge entry to 2 sumps are
28,67 m
3
/second (Quarter I ), 28,7 m
3
/ second (QuarterII), 28,7 m
/ second
(Quarter III) dan 30,5m
3
/ second (Quarter IV). Total discharge amount diverted
are 5,05 m
3
/second (Quarter I – IV). There are 2 open channels to prevent runoff
water did not get into the pit. Dimensions of open channel based on Manning’s
formula as shown below:
a. Open Channel I (RL 3) : h (hight ) = 1,5 m;
b ( width base) = 1,4 m;
B ( width top ) = 4 m
b. Open Channel II(Kelawitan ) : h ( hight ) = 1,2 m;
b ( width base ) = 1,1 m;
B ( width top ) = 3 m
Sump’s volume is calculated based on the number of water entry and
pumping discharge. Sump at Pit A Utara (Jeruk) used 3 line unit pump staging
(Multiflo MF-420E dan MF 385) for Quarter I – III and sump at Pit A Selatan
(Jeruk ) used 2 line unit pump staging (Multiflo MF-420E dan MF 385) for
Quarter I – III with debit total 584 m
3
/hour and sump volume 238.209,8 m
at
Pit A Utara ( Jeruk ) and 112.303,6 m
3
at Pit A Selatan (Anggrek), andthen for
Quarter IV needed 5 line unit pump staging with sump volume 350.513,4 m

.

3
3
3

Item Type: Thesis (Other)
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: Faculty of Engineering, Science and Mathematics > School of Engineering Sciences
Depositing User: Eko Yuli
Date Deposited: 12 May 2016 01:39
Last Modified: 13 Oct 2022 04:30
URI: http://eprints.upnyk.ac.id/id/eprint/700