KAJIAN TEKNIS SISTEM PENYALIRAN TAMBANG BATUBARA DI PT. BINA BARA SEJAHTERA DESA TANJUNG DALAM, KEC. ULOK KUPAI, KAB. BENGKULU UTARA, PROVINSI BENGKULU

PRABOWO, KADEK APRIANTO (2016) KAJIAN TEKNIS SISTEM PENYALIRAN TAMBANG BATUBARA DI PT. BINA BARA SEJAHTERA DESA TANJUNG DALAM, KEC. ULOK KUPAI, KAB. BENGKULU UTARA, PROVINSI BENGKULU. Other thesis, UPN "Veteran" Yogyakarta.

[thumbnail of 1 cover.pdf]
Preview
Text
1 cover.pdf

Download (176kB) | Preview
[thumbnail of 2 persembahan.pdf]
Preview
Text
2 persembahan.pdf

Download (179kB) | Preview
[thumbnail of 3 RINGKASAN.pdf]
Preview
Text
3 RINGKASAN.pdf

Download (77kB) | Preview
[thumbnail of 4 DAFTAR ISI.pdf]
Preview
Text
4 DAFTAR ISI.pdf

Download (172kB) | Preview

Abstract

Penelitian dilakukan pada Pit A PT. Bina Bara Sejahtera Jobsite PT. Firman
Ketaun. Pit ini berlokasi di Kecamatan Ulok Kupai, Kabupaten Bengkulu Utara
Provinsi Bengkulu. Kegiatan Penambangan Batubara di PT. Bina Bara Sejahtera
menggunakan sistem tambang terbuka dengan metode strip mining. Sistem
penyaliran yang digunakan adalah mine dewatering system. Sumber air berasal
dari air hujan, kemudian dikeluarkan dengan cara pemompaan. Saat musim hujan
sering terjadi genangan dan luapan air di lantai dasar tambang dikarenakan
volume air hujan yang masuk kedalam lokasi tambang cukup besar namun volume
sumuran tidak cukup untuk menampung air yang masuk. Oleh karena itu perlu
adanya kajian terhadap sistem penyaliran tambang yang ada.
Berdasarkan analisis data curah hujan tahun 2008 – 2014, diperoleh curah
hujan rencana adalah 109,7 mm/hari, intensitas curah hujan 41,81 mm/hari dengan
periode ulang hujan 3 tahun dan resiko hidrologi sebesar 86,9 %. Luas daerah
tangkapan hujan pada lokasi penelitian dibagi menjadi tiga daerah tangkapan
hujan, sebagai berikut : DTH I = 0,24 Km², DTH II = 0,17 Km², dan DTH III =
0,04 Km². Debit air limpasan pada setiap daerah tangkapan hujan sebagai berikut:
DTH I = 1,45 m³/detik, DTH II = 1,19 m³/detik, dan DTH III = 0,17 m³/detik.
Untuk mencegah supaya air tidak masuk ke area penambangan maka di buat
saluran terbuka di sekitar bukaan tambang. Kemudian untuk air yang masuk
kedalam bukaan tambang Pit A di alirkan secara alami ke sungai. Dimensi saluran
terbuka adalah sebagai berikut:
Saluran (Tenggara Pit A) : a = 1,18 m; b = 1,19 m; B = 2,95 m; h = 1,03 m; d =
0,86 m.
Volume sumuran dihitung berdasarkan jumlah air yang masuk dan debit
pemompaan. Pada sumuran di Pit A terdapat pompa Southern Cross dengan debit
pemompaan 200 m
3
/jam sehingga dapat ditentukan volume terbesar sumuran
adalah 1.861 m. Selanjutnya air pada sumuran dipompa menuju kolam
pengendapan yang memiliki luas 430 m² dan lamanya waktu pengerukan kolam
pengendapan adalah 18 hari.

The study was conducted on A pit, PT. Bina Bara Sejahtera Jobsite PT.
Firman Ketaun Coal Project. The pit is located at Ulok Kupai, Bengkulu Utara
Regency, Bengkulu. PT. Bina Bara Sejahtera uses surface mining system with
open pit methods. The drainage system which being used is mine dewatering
system. The water comes from rain which then be removed by pumping. During
the rainy season, there are often occurs water puddle and flood on the ground floor
of the mine due to the large volume of rainwater that enter the mine site, but the
volume of wells is not enough to accommodate the water. Therefore, a review of
the existing mine drainage system is really needed to solve the problem.
Based on the analysis of rainfall data from 2008 to 2014, the rainfall plan is
109,7 mm/day, 41,81 mm/day of rainfall intensity with a 3-year rainfall return
period and 86,9% of hydrology risk. There is three catchment area, they are : DTH
I = 0,24 km², DTH II = 0,17 km², and DTH III = 0,04 km². The runoff water
discharge in catchment are : DTH I = 1,45 m³/sec, DTH II = 1,19 m³/sec, and
DTH III = 0,17 m³/sec.
In order to prevent the water from entering the mine area, some open
channels are created around the opening of the mine. Then to the water that goes
into the mine pit openings A circulate naturally to the river. The open channel
dimensions are:
Channel : (southeast Pit A) : a = 1,18 m; b = 1,19 m; B = 2,95 m; h = 1,03 m;
d = 0,86 m.
Sump volume calculated based on the amount of water entered and pump
discharge. There is a Southern Cross pump in A pit well with pumping discharge
200 m
3
/h so that largest volume of sump could be determined for 1.861 m³.
Furthermore, the water in the sump are pumped toward the settling ponds which has an area of 430 m2 and the length of time dredging precipitation is 18 days.

Item Type: Thesis (Other)
Subjek: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: x. Faculty of Engineering, Science and Mathematics > School of Engineering Sciences
Depositing User: Eko Yuli
Date Deposited: 27 Sep 2016 04:04
Last Modified: 27 Sep 2016 04:04
URI: http://eprints.upnyk.ac.id/id/eprint/6789

Actions (login required)

View Item View Item