SABEKTI W.K, BAYU (2016) KAJIAN PENATAAN LAHAN DI LAHAN BEKAS TAMBANG PADA PERTAMBANGAN BATUBARA DI PT. BUKIT BAIDURI ENERGI KALIMANTAN TIMUR. Other thesis, UPN "Veteran" Yogyakarta.
| Preview | Text 1. JUDUL.pdf Download (99kB) | Preview | 
| Preview | Text 2. DAFTAR ISI.pdf Download (163kB) | Preview | 
| Preview | Text 3. ABSTRACK.pdf Download (85kB) | Preview | 
| Preview | Text pengesahan.pdf Download (72kB) | Preview | 
Abstract
The  observation  area  taken  place  in  mining  trace  area  of  batubara  in Senong  pit  which  located  in  Desa  Bukit  Pinang,  Kecamatan  Samarinda  Ulu, 
Kabupaten  Samarinda,  Provinsi  Kalimantan  Timur.  The  mining  in  Senong  pit used open mine method, which this mining method will leave cavities shape that it 
needs planning activity to structuring the land and revegetation.The purpose of this observation are planning the way to structuring land of the  mining  trace  area  that  consist  of  hoarding,  struct uring  the  top  of  soil  and planting in order to the revegation activity can work well.The  method  of  observation  by  using  combination  of  theory  that  have 
studied  by  used  data  that  taken  from  field  that  it  processed  and  analyzed  so  it 
getting approach to solve the problems. 
The  large  of  Senong  pit  which  revegetated  are  288.900  m2 by  material volume which needed to hoarding are 4.211.365,125 m2 . The hoard material from 
over  burden  pit  Jongkang.  The  diplacement  of  material  use  excavator  backhoe 
Komatsu PC300LC-8 2 units, Bulldozer Komatsu D85ESS-2 1 unit with chump truck Isuzu FVZ34P 10 units. The times that needed to wreck the materials  over 
burden  use excavator backhoe PC300LC-8 along 25 months 12 days. The structuring top of soil used guludan system by  the amount of guludan which needed for 28,89 hectare of large of land are 3.438  gulud by the amount of 
per  hectare  are  119  gulud,  the  volume  total  of  top  soil  which  needed  are 
27.503,1848  Lcm, the dimension of guludan  that is the long of guludan = 11  m ; the wide of beam = 1 m ; the tall = 0,5 m ; the layer of triangle = 0,5 m ; the wide 
of bottom = 0,5 m ; the wide between guludan = 5 m. The structuring top of soil 
made by combined human energy and heavy equipment . the times of structuring 
top of soil by  combination of human energy and heavy equipment are 4 months 17
days.  The  plants  which  used  to  doing  revegation  are  sengon  plant (paraserienthesfalcataria). The  requirement  of  sengon  plant  grows  is  seen  from 
the parameter of soil pH, texture of soil, efective of depth, air temperature, and 
high.
| Item Type: | Thesis (Other) | 
|---|---|
| Subjek: | T Technology > TA Engineering (General). Civil engineering (General) | 
| Divisions: | x. Faculty of Engineering, Science and Mathematics > School of Engineering Sciences | 
| Depositing User: | Eko Yuli | 
| Date Deposited: | 19 Jul 2016 03:14 | 
| Last Modified: | 19 Jul 2016 03:14 | 
| URI: | http://eprints.upnyk.ac.id/id/eprint/4825 | 
Actions (login required)
|  | View Item |