RENCANA KEBUTUHAN ALAT MUAT DAN ALAT ANGKUT PADA TAMBANG TANAH URUG PT ANUGRAH WAHYU PANDANARAN, KLATEN, JAWA TENGAH

TURNIP, OSCAR APRIYANDO (2024) RENCANA KEBUTUHAN ALAT MUAT DAN ALAT ANGKUT PADA TAMBANG TANAH URUG PT ANUGRAH WAHYU PANDANARAN, KLATEN, JAWA TENGAH. Other thesis, UPN Veteran Yogyakarta.

[thumbnail of Cover Oscar Apryando Turnip 112170039.pdf] Text
Cover Oscar Apryando Turnip 112170039.pdf

Download (94kB)
[thumbnail of Daftar Isi Oscar Apryando Turnip 112170039.pdf] Text
Daftar Isi Oscar Apryando Turnip 112170039.pdf

Download (206kB)
[thumbnail of Daftar Pustaka Oscar Apryando Turnip 112170039.pdf] Text
Daftar Pustaka Oscar Apryando Turnip 112170039.pdf

Download (169kB)
[thumbnail of Lembar Pengesahan Oscar Apriyando Turnip 112170039.pdf] Text
Lembar Pengesahan Oscar Apriyando Turnip 112170039.pdf

Download (1MB)
[thumbnail of Ringkasan Oscar Apryando Turnip 112170039.pdf] Text
Ringkasan Oscar Apryando Turnip 112170039.pdf

Download (182kB)
[thumbnail of Skripsi Oscar Apriyando Turnip 112170039.pdf] Text
Skripsi Oscar Apriyando Turnip 112170039.pdf
Restricted to Repository staff only

Download (5MB)

Abstract

v
RINGKASAN
Proyek pembangunan jalan tol Yogyakarta-Solo saat ini memerlukan material
dalam jumlah besar, satu di antaranya adalah tanah urug. PT Anugrah Wahyu
Pandanaran adalah salah satu perusahaan tambang dengan komoditas tanah urug
yang akan beroperasi dengan menyuplai tanah urug untuk proyek tersebut dan
memiliki target 135,90 LCM/jam.
Sebelum beroperasi, PT Anugrah Wahyu Pandanaran perlu mengetahui
jumlah alat muat dan alat angkut yang diperlukan untuk mencapai target produksi
sebesar 135,90 LCM/jam. Hal tersebut perlu dilakukan analisis terhadap faktor-
faktor yang mempengaruhi kegiatan pemuatan dan pengangkutan, serta
menghitung produksi dan juga keserasian kerja antara alat muat dan alat angkut.
Kegiatan pemuatan dan pengangkutan PT Anugrah Wahyu Pandanaran akan
menggunakan Excavator Kobelco SK 200-8 sebagai alat muat dan juga dump truck
Mitsubishi Colt Diesel 136 PS sebagai alat angkut. Berdasarkan analisis dan
perhitungan yang dilakukan menunjukkan waktu edar alat muat sebesar 17,83 detik
dengan efisiensi 73,28%, alat angkut sebesar 4.710,02 detik atau 1,31 jam serta
berjarak tempuh ± 17,6 km dan efisiensi 71,85%.
Hasil perhitungan, kemampuan produksi alat muat sebesar 150,47 LCM/jam
dan alat angkut 5,58 LCM/jam. Jumlah kebutuhan alat berdasarkan perhitungan
adalah sebanyak 2 unit alat muat (1 unit bekerja di lapangan dan 1 unit sebagai
cadangan) sedangkan alat angkut sebanyak 29 unit (25 unit yang bekerja di
lapangan dan 4 unit sebagai cadangan) dengan keserasian kerja alat muat dan alat
angkut sebesar 0,94 serta terdapat waktu tunggu alat muat 10,10 detik.
vi
SUMMARY
The Yogyakarta-Solo freeway construction project currently requires a large
quantity of materials, one of which is urug soil material. PT Anugrah Wahyu
Pandanaran is one of the mining companies specializing in urug soil material
commodities that will operate with the aim of supplying backfill soil for the project
and has a target of 135.90 LCM/hour.
Before commencing operations, PT Anugrah Wahyu Pandanaran needs to
determine the number of loader and hauler required to achieve the production
target of 135.90 LCM/hour. This requires an analysis of the factors influencing the
loading and transportation activities, as well as calculating production and the
compatibility of the loader and hauler.
PT. Anugrah Wahyu Pandanaran's loading and hauling activities will utilize
the Kobelco SK 200-8 Excavator as the loader and Mitsubishi Colt Diesel 136 PS
dump truck as the hauler. Based on the analysis and calculations, the cycle time for
the loader is 17.83 seconds with an efficiency of 73.28%, the hauler is
4,710.02 seconds and the haul road length ± 17.6 kilometers with an efficiency of
71.85%.
The result of production calculation from the loader was 150.47 LCM/hour
and 5.58 LCM/hour for the hauler. Total acquired requirements of loader is 2 units
(1 unit operating in the field and 1 unit as reserve), and 29 units for hauler (25 units
operating in the field and 4 units as reserves) with a match factor of 0.94 and the
waiting time for the loader is 10.10 seconds.

Item Type: Thesis (Other)
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: Faculty of Engineering, Science and Mathematics > School of Engineering Sciences