ANALISIS PARAMETER KEEKONOMIAN PADA LAPANGAN “ACM” DENGAN MENGGUNAKAN METODE PRODUCTION SHARING CONTRACT UNTUK PERPANJANGAN CONTRACT

MANGINDAAN, A. CAKRA (2024) ANALISIS PARAMETER KEEKONOMIAN PADA LAPANGAN “ACM” DENGAN MENGGUNAKAN METODE PRODUCTION SHARING CONTRACT UNTUK PERPANJANGAN CONTRACT. Other thesis, UPN Veteran Yogyajarta.

[thumbnail of Abstrak_113190008_A. Cakra Mangindaan.pdf] Text
Abstrak_113190008_A. Cakra Mangindaan.pdf

Download (416kB)
[thumbnail of Cover_113190008_A. Cakra Mangindaan.pdf] Text
Cover_113190008_A. Cakra Mangindaan.pdf

Download (161kB)
[thumbnail of Daftar Isi_113190008_A. Cakra Mangindaan.pdf] Text
Daftar Isi_113190008_A. Cakra Mangindaan.pdf

Download (518kB)
[thumbnail of Daftar Pustaka_113190008_A. Cakra Mangindaan.pdf] Text
Daftar Pustaka_113190008_A. Cakra Mangindaan.pdf

Download (329kB)
[thumbnail of Lembar Pengesahan_113190008_A. Cakra Mangindaan.pdf] Text
Lembar Pengesahan_113190008_A. Cakra Mangindaan.pdf

Download (137kB)
[thumbnail of Skripsi Full Text_113190008_A. Cakra Mangindaan.pdf] Text
Skripsi Full Text_113190008_A. Cakra Mangindaan.pdf
Restricted to Repository staff only

Download (2MB)

Abstract

vi
RINGKASAN
ANALISIS PARAMETER KEEKONOMIAN PADA
LAPANGAN “ACM” DENGAN MENGGUNAKAN METODE
PRODUCTION SHARING CONTRACT UNTUK
PERPANJANGAN CONTRACT
Oleh
A. Cakra Mangindaan
NIM: 113190008
(Program Studi Sarjana Teknik Perminyakan)
Lapangan “ACM” terletak di kota Prabumulih. Lapangan ACM merupakan salah
satu lapangan lama dan akan dilakukan optimasi pengembangan lapangan untuk
mendapatkan produksi yang lebih besar. Lapangan ini yang akan diproduksikan
pada 2023 hingga 2041. Lapangan ACM terletak di cekungan Sumatera Selatan
Lapangan ini direncanakan akan mengebor dengan total 14 sumur dengan
estemasikan akan memproduksikan 11839 MSTB. Dengan produksi tersebut akan
dilakukan analisa keekonomian dengan membandingkan perhitungan dan analisa
antara PSC gross split dengan PSC cost recovery untuk mengetahui PSC yang lebih
memberikan keuntungan.
Metode Penelitian yang digunakan meliputi studi analisa terhadap perhitungan
keekonomian pada Lapangan “ACM” menggunakan skema PSC Cost Recovery dan
PCS Gross Split. Tahapan perhitungan yakni pengumpulan data lapangan dan data
keeokonomian, perhitungan depresiasi terhadap nilai investasi capital, membuat
cash flow menggunakan metode PSC Cost Recovery dan Gross Split, dilanjutkan
dengan analisa keekonomian dengan membandingan indikator keekonomian
lapangan.
Dari hasil perhitungan didapatkan untuk PSC cost recovery nilai NPV sebesar 78,25
MM USD, NPV @10% 36 MM USD, IRR sebesar 46%, PIR sebesar 1,03, DPIR
sebesar 0,48, dan POT sebesar 1,9 tahun. Sedangkan untuk PSC gross split nilai
NPV sebesar 220,6 MM USD, NPV @10% 109,7 MM USD, IRR sebesar 76%,
PIR sebesar 2,9, DPIR sebesar 1,4, dan POT sebesar 1,7 tahun
Kata kunci: cash flow, cost recovery, gross split
vii
ABSTRACT
ANALYSIS OF ECONOMIC PARAMETERS IN THE FIELD
"ACM" USING THE PRODUCTION SHARING CONTRACT
FOR CONTRACT EXTENSION
By
A. Cakra Mangindaan
NIM: 113190008
(Petroleum Engineering Undergraduated Program)
The field "ACM" is located in the city of Prabumulih. ACM field is one of the old
fields and will be optimized for field development to get greater production. This
field will be produced in 2023 to 2041. ACM field is located in the South Sumatra
basin This field is planned to drill a total of 14 wells with the estimation to produce
11839 MSTB. With this production, an economic analysis will be carried out by
comparing calculations and analysis between gross split PSC and cost recovery
PSC to find out which PSC provides more benefits.
The research method used includes analytical studies on economic calculations in
the "ACM" Field using the PSC Cost Recovery and PCS Gross Split schemes. The
calculation stages are collecting field data and economic data, calculating
depreciation of capital investment value, making cash flow using the PSC Cost
Recovery and Gross Split methods, followed by economic analysis by comparing
field economic indicators.
From the calculation results, it is obtained for PSC cost recovery NPV value of
78.25 MM USD, NPV @ 10% 36 MM USD, IRR of 46%, PIR of 1.03, DPIR of 0.48,
and POT of 1.9 years. Meanwhile, for PSC gross split, NPV value is 220.6 MM
USD, NPV @10% 109.7 MM USD, IRR is 76%, PIR is 2.9, DPIR is 1.4, and POT
is 1.7 years.
Keywords: cash flow, cost recovery, gross split

Item Type: Thesis (Other)
Uncontrolled Keywords: cash flow, cost recovery, gross split
Subjects: T Technology > T Technology (General)
Divisions: Faculty of Engineering, Science and Mathematics > School of Engineering Sciences
Depositing User: Eko Yuli
Date Deposited: 26 Jan 2024 02:40
Last Modified: 26 Jan 2024 02:40
URI: http://eprints.upnyk.ac.id/id/eprint/38764

Actions (login required)

View Item View Item