RUSDY, NOVIANDI (2023) OPTIMASI DAN RANCANGAN KEMAJUAN PENAMBANGAN BIJIH NIKEL PADA TAMBANG TERBUKA BLOK PEBOA PT. DJAVA BERKAH MINERAL KECAMATAN PETASIA TIMUR, KABUPATEN MOROWALI UTARA, SULAWESI TENGAH. Other thesis, UPN "Veteran" Yogyajarta.
Text
Abstrak_Noviandi Rusdy_112180009.pdf Download (73kB) |
|
Text
Cover_Noviandi Rusdy_112180009.pdf Download (118kB) |
|
Text
Daftar Isi_Noviandi Rusdy_112180009.pdf Download (102kB) |
|
Text
Lembar Pengesahan_Noviandi Rusdy_112180009.pdf Download (227kB) |
|
Text
Daftar Pustaka_Noviandi Rusdy_112180009.pdf Download (148kB) |
|
Text
Final Draft_Noviandi Rusdy_112180009.pdf Restricted to Repository staff only Download (11MB) |
Abstract
v
RINGKASAN
PT Djava Berkah Mineral (PT DBM) merupakan perusahaan yang bergerak
dibidang kontraktor pertambangan dengan komoditas utama nikel laterit.
Perusahaan ini berada di Kecamatan Petasia Timur, Kabupaten Morowali Utara,
Provinsi Sulawesi Tengah. Penelitian yang dilakukan pada blok peboa merupakan
Project PT Bukit Makmur Istindo Nikeltama (PT BUMANIK) dengan Luas IUP
pada blok peboa 887,6 Ha.
Area tambang terbuka yang ada di blok peboa akan dilakukan penambangan
dengan metode open cast mining dengan cara selective mining. Metode open cast
ini dilakukan dengan medan kerja yang digali dari bawah ke atas atau sebaliknya
(side hill) dikarenakan endapan bijih yang berada di daerah bukit. Persebaran bijih
nikel yang terdapat pada area ini yaitu heterogen sehingga cara penambangan perlu
dilakukan secara selektif (selective mining) untuk menghindari terjadinya dilusi.
Tujuan penelitian ini adalah melakukan optimasi tambang terbuka sehingga
diperoleh rekomendasi pitshell. Pitshell optimal digunakan sebagai acuan rencana
dan rancangan tambang, rancangan jalan angkut dan rancangan area penimbunan.
Kemajuan tambang dibuat selama 17 bulan dengan target produksi 150.000
ton/bulan.
Metode penambangan yang digunakan untuk Blok Peboa adalah open cast.
Geometri jenjang yang digunakan sesuai dengan rekomendasi perusahaan yaitu
tinggi jenjang 6m, lebar jenjang 3m, kemiringan jenjang tunggal 56o, dan
kemiringan jenjang keseluruhan 45o. Geometri lebar minimum jalan angkut pada
jalan lurus 12m dan lebar jalan angkut pada tikungan 17,5m dengan besarnya
kemiringan grade jalan maksimal sebesar 12%. Pengolahan data dilakukan dengan
bantuan perangkat lunak Micromine 2023 dengan metode Lerch-Grossman.
Hasil rancangan tambang didapatkan dari pitshell pertama dengan nilai NPV
(Net Present Value) sebesar $17.995.462, dan IRR (Internal Rate Return) 20,90%.
Hasil cadangan berdasarkan rancangan tambang didapatkan bijih nikel sebesar
2.583.912 ton dan batuan sisa sebesar 2.558.723 ton dengan stripping ratio
0,99 yang akan dibagi menjadi 17 bulan. Alat muat yang digunakan pada
pengupasan lapisan tanah penutup adalah Excavator Komatsu PC300 dan alat
angkut MercedezBenz Axor 2528C. Untuk pengupasan bijih menggunakan alat
muat Excavator Komatsu PC 300 dan alat angkut UD QUESTER CWE 370.
vi
SUMMARY
PT Djava Berkah Mineral (PT DBM) is a company engaged in mining
contractors with the main commodity of nickel laterite. The company is located in
East Petasia District, North Morowali Regency, Central Sulawesi Province. The
research conducted on the peboa block. It was owned by PT Bukit Makmur Istindo
Nikeltama Project (PT BUMANIK) with an IUP area of 887.6 Ha.
The surface area in the peboa block will be mined using the open cast mining
method by selective mining. This open cast method is carried out with a working
field that is excavated from bottom to top and vice versa (side hill) due to ore
deposits located in the hill area. The distribution of nickel ore in this area is
heterogeneous so that the mining method needs to be done selectively (selective
mining) to avoid dilution.
The purpose of this research is to optimize the open pit mine to obtain
pitshell recommendations. The optimal pitshell is used as a reference for mining
plan and design, haul road design and stockpile area design. The mining progression
is made for 17 months with a production target of 150,000 tons/month.
The mining method used for the Peboa Block is open cast. The level
geometry used is in accordance with the company's recommendations, namely level
height of 6m, level width of 3m, single level slope of 56o, and overall level slope of
45o. The geometry of the minimum width of the haul road on a straight road is 12m
and the width of the haul road on a turn is 17.5m with a maximum road grade slope
of 12%. Data processing is done with the help of Micromine 2023 software with
the Lerch-Grossman method.
The mining design results were obtained from the first pitshell with an NPV
(Net Present Value) value of $17,995,462, and an IRR (Internal Rate Return) of
20.90%. Reserve results based on mining design obtained nickel ore of 2,583,912
tons and waste rock of 2,558,723 tons with a stripping ratio of 0.99 which will be
divided into 17 months. The loading equipment used in waste stripping is Komatsu
PC300 Excavator and Mercedez Benz Axor 2528C hauling equipment. For ore
stripping, Komatsu PC 300 excavator and UD QUESTER CWE 370 hauling
equipment are used.
Item Type: | Thesis (Other) |
---|---|
Subjects: | T Technology > TA Engineering (General). Civil engineering (General) |
Divisions: | Faculty of Engineering, Science and Mathematics > School of Engineering Sciences |
Depositing User: | Eko Yuli |
Date Deposited: | 11 Jul 2023 06:55 |
Last Modified: | 11 Jul 2023 06:55 |
URI: | http://eprints.upnyk.ac.id/id/eprint/36393 |
Actions (login required)