Suci Larasati, Nur (2014) ANALISIS DAYA TAMPUNG PADA PROSES SEDIMENTASI SETTLING POND 15 WESTBLOCK AREA DI PERUSAHAAN BATUBARA PT INDOMINCO MANDIRI, BONTANG, KALIMANTAN TIMUR. Other thesis, UPN ''VETERAN'' YOGYAKARTA.
Preview |
Text
Abstrak Skripsi.pdf Download (161kB) | Preview |
Abstract
Kegiatan penambangan di Pit 6SW dan Pit 2C yang semakin meningkat
menyebabkan menurunnya kualitas air limpasan yang masuk ke dalam Settling Pond 15.
Settling Pond 15 yang sebelumya terdiri atas 3 kompartemen, pada Juni 2013 dilakukan
penambahan kompartemen serta perubahan lokasi titik penaatan. Perubahan tersebut
bertujuan untuk meningkatkan daya tampung air limpasan serta kualitas air olahan.
Namun upaya tersebut belum tuntas mengontrol kualitas air olahannya, dimana nilai
TSS pada outlet seringkali masih melebihi baku mutu. Tujuan penelitian adalah untuk
mengkaji kualitas air Settling Pond 15 dengan parameter TSS sehingga dapat diketahui
besarnya efisiensi sedimentasi serta prakiraan volume lumpur yang dihasilkan, mengkaji
kesesuaian daya tampung Settling Pond 15 sesuai dengan debit air yang masuk dan
kriteria desain ideal kolam pengendapan, selain itu juga mengkaji penanganan air
limbah yang tepat untuk meningkatkan daya tampung Settling Pond 15 dalam proses
sedimentasi.
Metode penelitian yang digunakan dalam penelitian antara lain: metode survey,
sampling dan analisis laboratorium, metode kuantitatif perhitungan matematis, dan studi
komparatif antara objek di lapangan dengan standar atau kriteria desain dan baku mutu
yang sudah ditetapkan. Beberapa parameter pendukung penelitian yang digunakan,
yaitu: curah hujan, debit air limpasan, TSS dan berat jenis sedimen, serta parameter
desain kolam pengendapan seperti waktu tinggal, beban permukaan, kecepatan aliran,
hidrolika bak (Bilangan Fraude dan Bilangan Reynold), serta beban ambang outlet.
Curah hujan harian rencana dengan periode ulang 5 tahunan pada lokasi
penelitian sebesar 85.440 mm/hari dan intensitas curah hujan dengan menggunakan
rumus mononobe diperoleh hasil sebesar 29,620 mm/jam. Analisis debit air limpasan
dengan menggunakan rumus rasional diperoleh hasil sebesar 20.232 m3/s. Dengan
demikian, Settling Pond 15 yang terdiri dari 4 kompartemen dirancang untuk
menampung dan mengolah air dengan nilai debit tersebut. Selanjutnya dari hasil
penelitian diketahui bahwa kolam pengendapan pada Settling Pond 15 tidak memenuhi
kriteria desain ideal. Hal tersebut dikarenakan kompartemen Settling Pond 15 dirancang
untuk memenuhi debit rencana yang tinggi (sebesar 5.05 m3/s), namun debit
pemompaan aktual harian yang masuk ke inlet lebih rendah (sebesar 0.47 m3/s).
Rendahnya nilai debit yang masuk menyebabkan parameter waktu detensi, beban
permukaan, serta Bilangan Fraude ataupun Bilangan Reynold tidak terpenuhi sehingga
perlu dilakukan perbaikan serta arahan pengelolaan untuk meningkatkan daya tampung
pada proses sedimentasi kolam pengendapan.
Kata kunci: Settling pond, kriteria desain, daya tampung
The improving of mining in Pit 6SW and Pit 2C made decreasing of run off
quality into settling pond 15. That is reason of settling pond 15 in juni 2013 got upgrade,
the upgrade are additional compartment and reordering area. The settling pond 15 was
having 3 compartment. But, it is not complish for controlling water quality, because of
TSS grade in outlet was over limit of the water standard oftenly. The aim of study are
inspecting water quality in setlling pond 15 with TSS parameter (it to know
sedimentations efficient and to suppose mud volume result), inspecting capacity of
settling pond like as design criterias, and to inspect waste water treatment for improving
settling pond capacity in sedimentation process.
The methods of study are survey, sampling, laboratory analisys and quantitative
method (calculating of mathematics and comparing between object in the field to
standard or design criteria and the limit). The parameters are rainfall, run off cumecs,
TSS, weightness of sediment, and desing of settling pond.After that analisys, there is
analisys of settling pond with criteria like as settle treatment time (time for
sedimentation process in settling pond), surface weight material, water velocity, hidrolic
pond (Fraude an Reynold Numbers), and outlet limit weightness.
Daily rainfall planning on the study’s location of reperiod in 5 years is 85.440
mm/day and by using mononobe pattern rainfall intensity is 26.620 mm/hour. Analisys of run
off cumecs by using rasional pattern the result is 20.232 m3/s, so that design of settling
pond 15 to accommodate and to treatment water like that result was made 4
compartments to be. After that analisys, there is analisys of settling pond with criteria
like as settle treatment time was not accomplish standard limit (ideal limits).
Compartment 15 was designed for high recharge water plan (5.05 m3/s), but in actual
recharge pumping daily that flow into inlet was lower than it (0.47 m3/s). it made
parameter ( detention time, Surface weightness, Fraude, and Reynold Numbers) was not
accomplish, and it had to be fixed and managed to improve capacity of sedimentation
process in settling pond.
Key Words : Settling pond, Design Criteria, Capacity.
Item Type: | Thesis (Other) |
---|---|
Subjek: | T Technology > TD Environmental technology. Sanitary engineering |
Divisions: | x. Faculty of Engineering, Science and Mathematics > School of Civil Engineering and the Environment |
Depositing User: | Erny Azyanti |
Date Deposited: | 10 Jun 2016 06:28 |
Last Modified: | 10 Jun 2016 06:28 |
URI: | http://eprints.upnyk.ac.id/id/eprint/3579 |
Actions (login required)
![]() |
View Item |