PENCAPAIAN TARGET PRODUKSI PENGUPASAN TANAH PENUTUP PADA TAMBANG BATUBARA DI KPUC PROJECT PT. MADHANI TALATAH NUSANTARA KALIMANTAN TIMUR

WIDYA WIROTTAMA, RIO (2011) PENCAPAIAN TARGET PRODUKSI PENGUPASAN TANAH PENUTUP PADA TAMBANG BATUBARA DI KPUC PROJECT PT. MADHANI TALATAH NUSANTARA KALIMANTAN TIMUR. Other thesis, UPN "Veteran" Yogyakarta.

[img]
Preview
Text
RINGKASAN.pdf

Download (51kB) | Preview
[img]
Preview
Text
abstract.pdf

Download (9kB) | Preview
[img]
Preview
Text
DAFTAR_ISI.pdf

Download (10kB) | Preview
[img]
Preview
Text
sampul.pdf

Download (79kB) | Preview
[img]
Preview
Text
Pengesahan.pdf

Download (38kB) | Preview

Abstract

PT. Madhani Talatah Nusantara merupakan suatu perusahaan kontraktor di bidang penambangan batubara. Lokasi penambangan terletak di Desa Mulawarman, Kecamatan Tenggarong Seberang, Kabupaten Kutai Kartanegara, Provinsi Kalimantan Timur. PT. Madhani Talatah Nusantara (PT.MTN) mengerjakan usaha penambangan batubara milik PT. Kayan Putra Utama Coal sejak pertengahan Agustus 2009 dengan luas wilayah pertambangan 651 ha. Kegiatan pengupasan tanah penutup dilakukan dengan menggunakan 3 unit alat muat yaitu 3 unit backhoe Hitachi 3600 dan 2 unit backhoe Hitachi 2500. Sedangkan untuk alat angkutnya menggunakan 15 unit Caterpillar 785C dan 16 unit Caterpillar 777D. Target produksi yang harus dicapai oleh rangkaian alat muat dan alat angkut adalah 3.261.654 BCM/bulan. Produksi aktual dari rangkaian alat tersebut hanya 2.489.615 BCM/bulan, sehingga masih terdapat kekurangan 772.039 BCM. Hal ini disebabkan karena adanya waktu-waktu hambatan yang menyebabkan berkurangnya waktu kerja efektif alat. Efisiensi kerja alat muat yakni 69,4 % sedangkan alat angkut 73,7 %. Nilai efisiensi tersebut dikategorikan dalam kategori yang tidak menguntungkan. Upaya yang dilakukan guna mencapai target produksi dan meningkatkan nilai efisiensi kerja yakni dengan memperbaiki waktu kerja efektif alat muat dan alat angkut. Upaya perbaikan ini dilakukan dengan 2 tahap. Tahap 1 dilakukan dengan mengurangi waktu hambatan yang dapat dihindari namun tanpa mengurangi waktu hambatan berupa waktu menunggu truk. Perbaikan tahap 2 dilakukan dengan cara mengurangi waktu hambatan karena menunggu truk. Perbaikan tahap 2 dilakukan bila ternyata perbaikan tahap 1 belum dapat menghasilkan pencapaian terhadap target produksi dan belum dapat meningkatkan kategori atas efisiensi kerja alat muat dan alat angkut. Hasil yang didapat setelah dilakukan perbaikan waktu kerja efektif tahap 1 ialah peningkatan jumlah produksi menjadi 2.563.189,5 BCM. Rata-rata efisiensi kerja alat muat meningkat menjadi 71,6 % sedangkan untuk alat angkut menjadi 76%. Namun nilai efisiensi alat muat ini masih tetap dikategorikan dalam kategori yang tidak menguntungkan. Belum tercapainya target produksi dan masih rendahnya efisiensi kerja alat muat menyebabkan perlunya dilakukan perbaikan waktu kerja efektif tahap 2. Perbaikan waktu kerja efektif tahap 2 dilakukan dengan mengurangi waktu hambatan karena menunggu truk. Ini dilakukan dengan menambahkan 11 unit dumptruck Caterpillar 777D yang berasal dari proyek lain PT. MTN yang akan habis umur tambangnya. Dengan hal ini, pencapaian produksi meningkat menjadi 3.370.053 BCM/bulan. Nilai efisiensi kerja alat muat pun mengalami peningkatan menjadi 75,82%, nilai ini sudah dapat dikategorikan dalam kategori sedang. Dengan ini dapat diketahui bahwa waktu kerja efektif alat muat dan alat angkut telah meningkat menjadi kategori sedang dan target produksi yang ditetapkan sudah berhasil dipenuhi. ABSTRACT PT. Madhani Talatah Nusantara is a contractors company in the field of coal mining. Mining sites located in the Village Mulawarman, District Tenggarong Seberang, Kutai regency, East Kalimantan province. PT. Madhani Talatah Nusantara (PT.MTN) working on the coal mining business of PT. Kayan Putra Utama Coal since mid-August 2009 with a mining area of 651 ha. Overburden stripping activities carried out by using 3 units backhoe Hitachi 3600 and 2 units backhoe Hitachi 2500. As for hauling equipments using 15 units Caterpillar 785C and 16 units Caterpillar 777D. Production targets to be achieved is 3.261.654 BCM/month. Actual production of a series of equipments that only 2.489.615 BCM /month, so there is still a shortage of 772,039 BCM. This is due to time constraints which cause a reduction in effective working time of equipments. Work efficiency of loading equipment is 69,4% and 73.7% of transport equipment. Work efficiency values are categorized in categories that are not profitable. Efforts are made to achieve production targets and increase work efficiency value by improving the effective working time of loading and hauling equipments. Improvement efforts are done in 2 stages. Stage 1 is done by reducing the time constraints that can be avoided, but without reducing the barriers of time waiting for the truck. Improvements stage 2 is done by reducing the time constraints due to waiting trucks. Improvements stage 2 will be done if stage 1 improvements have not be able to produce the achievement of production targets and have not be able to increase the categories of work efficiency of loading and hauling equipments. The results obtained after stage 1 of repairing effective working time is increased the amount of production to be 2.563.189,5 BCM. The average efficiency of work equipments increased to be 71.6% loading, while for hauling equipments to be 76%. The work efficiency of the loading equipments is still classified in categories that are not profitable. Yet the achievement of production targets and low work efficiency of loading equipments caused the need for work effective repair stage 2. Repair of work time effectively stage 2 is done by reducing the barriers of time due to waiting trucks. This is done by adding 11 units of dumptruck Caterpillar 777D from another project of PT.MTN that will be depleted mine age. With this, the achievement of production increased to 3,370,053 BCM / month. Value of work efficiency of loading equipments has increased to 75,82%, this value can already be categorized in the category of medium. With this, it can be show that the effective working time of loading equipments and hauling equipments has risen to medium categories and production target has successfully achieve.

Item Type: Thesis (Other)
Subjects: T Technology > TN Mining engineering. Metallurgy
Divisions: Faculty of Engineering, Science and Mathematics > School of Engineering Sciences
Depositing User: Eny Suparny
Date Deposited: 08 Jun 2016 03:28
Last Modified: 08 Jun 2016 03:28
URI: http://eprints.upnyk.ac.id/id/eprint/3259