PANGESTU, WAHYU IDI (2022) KAJIAN OPTIMISASI PIT PADA PENAMBANGAN ANDESIT MENGGUNAKAN METODE LERCHS-GROSSMAN. Other thesis, UPN 'Veteran" Yogyakarta.
| ![[thumbnail of DAFTAR_ISI.PDF]](http://eprints.upnyk.ac.id/style/images/fileicons/text.png) | Text DAFTAR_ISI.PDF Download (153kB) | 
| ![[thumbnail of LEMBAR_PENGESAHAN.PDF]](http://eprints.upnyk.ac.id/style/images/fileicons/text.png) | Text LEMBAR_PENGESAHAN.PDF Download (148kB) | 
| ![[thumbnail of SKRIPSI_FULL_WAHYU_IDI_PANG.PDF]](http://eprints.upnyk.ac.id/style/images/fileicons/text.png) | Text SKRIPSI_FULL_WAHYU_IDI_PANG.PDF Restricted to Repository staff only Download (13MB) | 
| ![[thumbnail of COVER.PDF]](http://eprints.upnyk.ac.id/style/images/fileicons/text.png) | Text COVER.PDF Download (182kB) | 
| ![[thumbnail of ABSTRAK.PDF]](http://eprints.upnyk.ac.id/style/images/fileicons/text.png) | Text ABSTRAK.PDF Download (18kB) | 
| ![[thumbnail of DAFTAR_PUSTAKA.PDF]](http://eprints.upnyk.ac.id/style/images/fileicons/text.png) | Text DAFTAR_PUSTAKA.PDF Download (85kB) | 
Abstract
iv
RINGKASAN
Perencanaan jangka panjang suatu proyek pertambangan penting 
dilakukan untuk mencapai keberhasilan operasi pertambangan. Optimisasi bukaan 
tambang sebagai bagian dari perencanaan dilakukan untuk memaksimalkan Net 
Present Value (NPV). Penelitian dilakukan di PT. Gawi Maju Karsa (PT. GMK)
yang berlokasi di Dusun Pletuk, Desa Dadirejo, Kecamatan Bagelen, Kabupaten 
Purworejo, Provinsi Jawa Tengah. Permasalahan penelitian ini adalah
memaksimalkan proyek tambang dengan lapisan tanah penutup yang tebal dan 
target produksi yang telah ditetapkan berdasarkan pendapatan dan biaya. Tujuan 
dilakukannya penelitian ini meliputi validasi data, pit optimalization, rancangan 
desain kemajuan tambang, rancangan jalan angkut, rancangan area timbunan,
kebutuhan alat muat dan angkut. Pengolahan data dibantu menggunakan perangkat 
lunak Micromine 2022.
Validasi data dilakukan untuk data topografi, data lubang bor, model geologi,
dan block model andesit. Optimisasi bukaan tambang menggunakan metode 
Lerchs-Grossman dengan parameter mining, processing, dan customer sebagai 
inputan, rancangan kemajuan tambang dan timbunan dibuat selama 5 tahun dengan 
target produksi 360.000 BCM andesit, rancangan jalan angkut dan kebutuhan alat 
gali muat didasarkan teori Hustrulid. 
Validasi data yang dilakukan telah sesuai antar kondisi dilapangan dan data 
eksplorasi. Pit optimization menghasilkan 16 pit shell. Ultimate pit shell ditentukan 
berdasarkan nilai NPV, Internal Rate of Return (IRR), dan rencana teknis 
penambangan. Ultimate pit shell merupakan Pit shell stage-2 dengan nilai NPV Rp 
41.219.318.000. Metode penambangan yang digunakan adalah kuari bertipe open 
pit dengan geomteri jenjang penambangan yaitu meliputi sudut kemiringan jenjang 
tunggal 70°, tinggi jenjang tunggal 9,4 meter, dan lebar jenjang 6 meter. Total 
tertambang selama 5 tahun untuk andesit yaitu 1.860.000 BCM. Rancangan jalan 
angkut tambang dirancang berdasarkan alat angkut Hino FM 260 JD. Lebar jalan 
minimum pada lintasan lurus sebesar 9 meter dan pada lintasan berbelok 12,1 
meter, radius tikungan minimum 12,6 meter. Area timbunan dirancang mampu 
menampung tanah pucuk sebesar 97.320 CCM dan tanah penutup 742.965 CCM. 
Kebutuhan alat muat excavator Kobelco SK200XDL-10 untuk mencapai target 
produksi setiap tahunnya adalah 2 unit, kebutuhan alat angkut Dumptruck Hino FM 
260 JD tahun pertama sampai kedua berjumlah 5 unit, sedangkan tahun ketiga 
hingga kelima berjumlah 6 unit.
v
SUMMARY
Long-term planning of a mining project is important to achieve a successful 
mining operation. Optimization of mine openings as part of the planning is carried 
out to maximize the Net Present Value (NPV). The research was conducted at PT. 
Gawi Maju Karsa (PT. GMK) is located in Pletuk Hamlet, Dadirejo village, Bagel 
District, Purworejo Regency, Province of Central Java. The problem of this 
research is to maximize mining projects with thick overburden and production 
targets that have been set based on revenues and costs. The objectives of this 
research include data validation, pit optimization, progress design, haul road design, 
stockpile area design, and loading and unloading equipment requirements. Assisted 
data processing using Micromine 2022 software.
Data validation was carried out for topographic data, borehole data, 
geological models, and andesite block models. Optimization of mine openings 
using the Lerchs-Grossman method with mining, processing, and customer 
parameters as input, mine progress design and stockpile made for 5 years with a 
production target of 360,000 BCM andesite, haul road design, and digging 
equipment needs based on Hustrulid theory.
The data validation was carried out following the conditions in the field and 
data exploration. Pit optimization resulted in 16 pit shells. The ultimate pit shell is 
determined based on the NPV value, Internal Rate of Return (IRR), and the mining 
technical plan. The ultimate pit shell is a stage-2 pit shell with an NPV value of IDR 
43.900.000.000. The mining method used is an open pit type quarry with an 
observable geometry seen from a single slope angle of 70°, bench high 9,4 meters,
and bench width 6 meters. The total mined for 5 years for the andesite is 1.860.000 
BCM. The haul road design is based on the Hino FM 260 JD conveyance. The 
minimum road width on a straight track is 9 meters and on a turning track 12,1 
meters, and the minimum radius is 12,6 meters. The disposal area is designed to 
accommodate topsoil of 97.320 CCM and cover assistance of 742.965 CCM. The 
need for loading and unloading equipment for the Kobelco SK200XDL-10 
excavator to achieve the annual production target is 2 units, the need for Dumptruck 
Hino FM 260 JD in the first to second year total 5 units while the third to fifth year 
need total 6 units.
| Item Type: | Thesis (Other) | 
|---|---|
| Subjek: | T Technology > TA Engineering (General). Civil engineering (General) | 
| Divisions: | x. Faculty of Engineering, Science and Mathematics > School of Engineering Sciences | 
| Depositing User: | Eko Yuli | 