AKBAR, ABDUL MALIK (2022) KAJIAN MANAJEMEN RISIKO PADA KEGIATAN PENAMBANGAN BATUGAMPING UP. PARNO, KABUPATEN GUNUNGKIDUL, DIY. Other thesis, UPN 'Veteran" Yogyakarta.
| ![[thumbnail of Cover.pdf]](http://eprints.upnyk.ac.id/style/images/fileicons/text.png) | Text Cover.pdf Download (206kB) | 
| ![[thumbnail of DAFTAR ISI.pdf]](http://eprints.upnyk.ac.id/style/images/fileicons/text.png) | Text DAFTAR ISI.pdf Download (91kB) | 
| ![[thumbnail of DAFTAR PUSTAKA.pdf]](http://eprints.upnyk.ac.id/style/images/fileicons/text.png) | Text DAFTAR PUSTAKA.pdf Download (141kB) | 
| ![[thumbnail of LEMBAR PENGESAHAN.pdf]](http://eprints.upnyk.ac.id/style/images/fileicons/text.png) | Text LEMBAR PENGESAHAN.pdf Download (698kB) | 
| ![[thumbnail of Abstrak.pdf]](http://eprints.upnyk.ac.id/style/images/fileicons/text.png) | Text Abstrak.pdf Download (88kB) | 
| ![[thumbnail of Draft Skripsi Abdul Malik Akbar Fix Yudisium.pdf]](http://eprints.upnyk.ac.id/style/images/fileicons/text.png) | Text Draft Skripsi Abdul Malik Akbar Fix Yudisium.pdf Restricted to Repository staff only Download (3MB) | 
Abstract
RINGKASAN
Memasuki dunia industri yang semakin modern diikuti dengan 
perkembangan dan penerapan teknologi tinggi mempunyai hubungan yang erat 
dengan aktifitas pekerjanya. Unit Pertambangan Parno merupakan perusahaan
tambang perseorangan yang bergerak dibidang penambangan batugamping yang 
terletak di Desa Karangasem, Kecamatan Ponjong, Kabupaten Gunung Kidul, 
Daerah Istimewa Yogyakarta. Setiap kegiatan penambangan tentu memiliki risiko 
kecelakaan yang besar dan berbeda, maka dari itu untuk mengetahui potensi risiko 
diperlukan adanya manajemen risiko.
Penelitian ini dilakukan dengan tujuan untuk mengidentifikasi bahaya pada 
kegiatan penambangan, melakukan penilaian risiko pada tahap penambangan, dan 
melakukan upaya pengendalian risiko kecelakaan kerja pada tahap penambangan. 
Metode yang digunakan pada penelitian ini melalui beberapa tahap yaitu 
melakukan studi literatur, penyelidikan lapangan, pengambilan data primer dan 
sekunder dan pengolahan data. 
Identifikasi risiko dilakukan untuk menganalisis dampak yang akan
ditimbulkan dan cara mencegah agar tidak terjadi kecelakan kerja. Setelah 
melakukan identifikasi risiko, semua langkah kerja yang terdapat di UP Parno 
dinilai tingkat bahayanya. Dari hasil penilaian risiko didapatkan tingkat risiko pada 
tahap pembongkaran sebesar 62,5% risiko rendah, 25% risiko sedang, 12,5% risiko 
tinggi. Pada tahap pemuatan didapatkan nilai tingkat risiko sebesar 37,5% risiko 
rendah, 50% risiko sedang, 12,5% risiko tinggi. Pada tahap pengangkutan 
didapatkan nilai sebesar 14,29% risiko rendah, 42,85% risiko sedang, 28,57% risiko 
tinggi, dan 14,29% risiko ekstrim.
Dari hasil penelitian yang dilakukan, diperlukan adanya evaluasi program 
keselamatan dan kesehatan kerja lebih detil agar pekerja dapat melaksanakan kerja
secara sesuai dan dengan benar, serta dapat meminimalisir akan terjadinya 
kecelakan kerja dan sakit akibat kerja.
SUMMARY
Getting into an increasing industrial modern world followed by the 
development and the application of high technology has a close relationship with 
the activities of the workers. UP Parno is an individual mining company engaged 
in limestone mining that located in Karangasem area, Ponjong subdistrict, 
Gunungkidul regency, Yogyakarta Special Region. Every mining activity certainly 
has a large and different accident risk, therefore to know the potential risks it is 
necessary to have a risk management.
This study was conducted to identifying hazards in mining activities, 
conducting risk assessment in every mining stage, and making efforts to prevent 
work accident in every mining stage. The method used in this study went through 
several stages, which are literature studies, field investigations, primary and 
secondary data collecting, and data processing.
Risk identification is used to analyze the impact that will be caused and how 
to prevent work accidents would happend. After identifying the risks, the sequences 
of work steps in UP Parno are assessed for their hazard level. From the result of 
the risk assessment, the risk level of loosening stage are 62,5% low risk, 25% 
medium risk, 12,5% high risk. In the loading stage, the risk level show 37,5% low 
risk, 50% medium risk, 12,5% high risk. In the hauling stage, the risk level show 
14,29% low risk, 42,85% medium risk, 28,57% high risk, and 14,29% extreme.
From the results of the study, it is necessary to evaluate the safety and health 
program more detail so the workers can carry out their work well prepared and 
safely, and also can minimize the chance of the accident and work-related illnesses 
would happend.
| Item Type: | Thesis (Other) | 
|---|---|
| Uncontrolled Keywords: | Pertambangan | 
| Subjek: | T Technology > TA Engineering (General). Civil engineering (General) | 
| Divisions: | x. Faculty of Engineering, Science and Mathematics > School of Engineering Sciences | 
| Depositing User: | Eko Yuli | 
| Date Deposited: | 08 Jul 2022 06:37 | 
| Last Modified: | 08 Jul 2022 06:38 | 
| URI: | http://eprints.upnyk.ac.id/id/eprint/30340 | 