KAJIAN TEKNIS SISTEM PENYALIRAN TAMBANG PADA PENAMBANGAN ANDESIT DI KECAMATAN BALEENDAH, KABUPATEN BANDUNG, PROVINSI JAWA BARAT

FIRDASENA, DESSYFA (2022) KAJIAN TEKNIS SISTEM PENYALIRAN TAMBANG PADA PENAMBANGAN ANDESIT DI KECAMATAN BALEENDAH, KABUPATEN BANDUNG, PROVINSI JAWA BARAT. Other thesis, UPN 'Veteran" Yogyakarta.

[thumbnail of COVER_DESSYFA FIRDASENA.pdf] Text
COVER_DESSYFA FIRDASENA.pdf

Download (83kB)
[thumbnail of DAFTAR ISI_DESSYFA FIRDASENA.pdf] Text
DAFTAR ISI_DESSYFA FIRDASENA.pdf

Download (108kB)
[thumbnail of DRAFT SKRIPSI_DESSYFA FIRDASENA (1).pdf] Text
DRAFT SKRIPSI_DESSYFA FIRDASENA (1).pdf
Restricted to Repository staff only

Download (3MB)
[thumbnail of PENGESAHAN_DESSYFA FIRDASENA.pdf] Text
PENGESAHAN_DESSYFA FIRDASENA.pdf

Download (247kB)
[thumbnail of RINGKASAN_DESSYFA FIRDASENA.pdf] Text
RINGKASAN_DESSYFA FIRDASENA.pdf

Download (72kB)

Abstract

iv
RINGKASAN
Penelitian ini dilakukan di PD. Alam Jaya yang berlokasi di Kampung
Sukamelang, Kecamatan Baleendah, Kabupaten Bandung, Provinsi Jawa Barat.
Sistem penyaliran yang digunakan adalah mine dewatering dan mine drainage.
Sumber air tambang berasal dari air hujan dan air limpasan yang mengalir masuk
ke dalam pemuka kerja penambangan. Saat terjadi hujan dengan intensitas yang
tinggi, sering terjadi genangan air di lantai dasar tambang maupun di jalan angkut.
Hal ini disebabkan karena letak kolam pengendapan yang kurang tepat dan tidak
terdapat adanya saluran terbuka untuk mengalirkan air limpasan. Oleh sebab itu
perlu dilakukan kajian terhadap sistem penyaliran yang ada untuk dapat
merekomendasikan dimensi saluran terbuka dan kolam pengendapan yang tepat.
Penelitian ini menggunakan data curah hujan tahun 2011-2020 untuk dapat
menganalisis curah hujan rencana dan intensitas curah hujan. Berdasarkan hasil
analisis menggunakan metode Log Pearson Type III diperoleh curah hujan rencana
sebesar 95,127 mm/hari. Intensitas sebesar 32,979 mm/jam dengan periode ulang 3
tahun dan resiko hidrologi 86% dihitung menggunakan rumus Mononobe. Daerah
tangkapan hujan pada lokasi penelitian dibagi menjadi tiga bagian, yaitu sebagai
berikut : DTH 1 = 0,037 km2
, DTH 2 = 0,079 km2
, dan DTH 3 = 0,006 km2
. Debit
air limpasan sebesar 0,599 m3
/detik. Dimensi saluran terbuka dihitung
menggunakan rumus Manning.
Setelah dilakukan kajian terhadap sistem penyaliran tambang, diperoleh
rekomendasi penambahan panjang pada saluran terbuka 1 sebesar 110 m dan
dibutuhkan adanya rancangan dimensi saluran terbuka untuk mencegah masuknya
air ke dalam pemuka kerja penambangan dengan ukuran sebesar α = 60°, d = 0,5
m, h = 0,6 m, B = 1,15 m, b = 0,6 m, dan ɑ = 0,7 m. Kolam pengendapan yang
semula terletak di tengah pemuka kerja penambangan ditutup dengan menggunakan
tanah urug, kemudian rancangan kolam pengendapan yang merupakan rekomendasi
dari hasil kajian diletakkan di luar pemuka kerja penambangan, dengan dimensi
yaitu luas sebesar 375 m2
dan kapasitas sebesar 831 m3
.

v
SUMMARY
This research was conducted in PD. Alam Jaya which is located in
Sukamelang Village, Baleendah District, Bandung Regency, West Java Province.
The drainage system used is mine dewatering and mine drainage. The source of
mine water comes from rainwater and runoff water that flows into the mining work
surface. When it rains with high intensity, water puddles often occur on the ground
floor of the mine and on the haul road. This is due to the improper location of the
settling pond and the absence of an open channel to drain the runoff water.
Therefore, it is necessary to study the existing drainage system to be able to
recommend the right dimensions of open channels and settling ponds.
This study uses rainfall data for 2011-2020 to be able to analyze planned
rainfall and rainfall intensity. Based on the results of the analysis using the Log
Pearson Type III method, the planned rainfall is 95.127 mm/day. The intensity of
32,979 mm/hour with a return period of 3 years and a hydrological risk of 86% was
calculated using the Mononobe formula. The rain catchment area at the study site
is divided into three parts, namely as follows: DTH 1 = 0.037 km2
, DTH 2 = 0.079
km2
, and DTH 3 = 0.006 km2
. The runoff water discharge is 0.599 m3
/second. The
dimensions of the open channel are calculated using the Manning formula.
After conducting a study on the mine drainage system, it was found that the
recommendation to increase the length of the open channel 1 by 110 m and it is
necessary to design an open channel dimension to prevent water from entering the
mining work surface with a size of = 60°, d = 0.5 m, h = 0.6 m, B = 1.15 m, b = 0.6
m, and = 0.7 m. The settling pond which was originally located in the middle of the
mining work leader was closed using fill soil, then the design of the settling pond
which was a recommendation from the results of the study was placed outside the
mining work surface, with dimensions of 375 m2
and a capacity of 831 m3
.

Item Type: Thesis (Other)
Uncontrolled Keywords: Sumber air tambang berasal dari air hujan dan air limpasan yang mengalir masuk ke dalam pemuka kerja penambangan
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: Faculty of Engineering, Science and Mathematics > School of Engineering Sciences
Depositing User: Eko Yuli
Date Deposited: 11 Apr 2022 07:16
Last Modified: 07 Sep 2022 04:21
URI: http://eprints.upnyk.ac.id/id/eprint/29462

Actions (login required)

View Item View Item