KAJIAN TEKNIS PRODUKTIVITAS ALAT MUAT DAN ALAT ANGKUT PADA TAMBANG ANDESIT CV. MUNCUL KARYA DESA SIDOMULYO, KECAMATAN PENGASIH, KABUPATEN KULON PROGO, DIY

HANDASAH, SITI (2022) KAJIAN TEKNIS PRODUKTIVITAS ALAT MUAT DAN ALAT ANGKUT PADA TAMBANG ANDESIT CV. MUNCUL KARYA DESA SIDOMULYO, KECAMATAN PENGASIH, KABUPATEN KULON PROGO, DIY. Other thesis, UPN 'Veteran" Yogyakarta.

[thumbnail of COVER_SITI HANDASAH.pdf]
Preview
Text
COVER_SITI HANDASAH.pdf

Download (247kB) | Preview
[thumbnail of DAFTAR ISI_SITI HANDASAH.pdf]
Preview
Text
DAFTAR ISI_SITI HANDASAH.pdf

Download (326kB) | Preview
[thumbnail of DAFTAR PUSTAKA_SITI HANDASAH.pdf]
Preview
Text
DAFTAR PUSTAKA_SITI HANDASAH.pdf

Download (7kB) | Preview
[thumbnail of SKRIPSI SITI HANDASAH_112170138-1.pdf] Text
SKRIPSI SITI HANDASAH_112170138-1.pdf
Restricted to Repository staff only

Download (2MB)
[thumbnail of RINGKASAN_SITI HANDASAH.pdf]
Preview
Text
RINGKASAN_SITI HANDASAH.pdf

Download (14kB) | Preview
[thumbnail of LEMBAR PENGESAHAN_SITI HANDASAH.pdf]
Preview
Text
LEMBAR PENGESAHAN_SITI HANDASAH.pdf

Download (387kB) | Preview

Abstract

v
RINGKASAN
CV. Muncul Karya adalah salah satu perusahaan yang bergerak dibidang
pertambangan batu Andesit di Desa Sidomulyo, Kec. Pengasih, Kab. Kulon Progo,
DIY. Sistem penambangan yang diterapkan oleh perusahaan tempat penelitian ialah
tambang terbuka dengan metode kuari. Kegiatan tersebut terdiri dari pembongkaran,
pemuatan, dan pengangkutan. Kegiatan pembongkaran dilakukan oleh rock breaker,
pemuatan dilakukan oleh excavator dan proses pengangkutan dilakukan oleh dump
truck. Masalah yang dihadapi oleh perusahaan ialah belum tercapainya target
produksi andesit sebesar 7.000 BCM/bulan. Belum tercapainya target produksi
penambangan andesit yang telah direncanakan tersebut oleh karena itu perlu
dilakukan analisa faktor dan hambatan yang menyebabkan belum tercapainya target
produsi serta melakukan upaya pencapaian target produksi.
Metode penelitian yang diterapkan pada kajian ini ialah dimulai dari studi
literatur, observasi langsung di lapangan untuk pengambilan data primer dan data
sekunder. Data yangdiperoleh dari lapangan kemudian dilakukan pengolahan dan
analisis data. Faktor-faktor yang mempengaruhi kegiatan produksi andesit adalah
nilai bucket fill factor yang rendah yaitu hanya 60%, efisiensi kerja alat yang rendah
yaitu pada alat muat sebesar 69% dan pada alat angkut sebesar 72%, serta adanya
material tanah penutup yang ada di dalam front penambangan yang menyebabkan
sempitnya ruang gerak pada alat angkut untuk bermanuver, sehingga terdapat waktu
tunggu pada alat muat saat alat angkut mengambil posisi untuk dimuati.
Produksi penambangan batu andesit pada perusahaan tempat penelitian pada
saat ini yaitu untuk 1 unit alat muat KOMATSU PC200 sebesar 4.827 BCM/bulan
dan untuk 10 unit alat angkut dump truck Toyota Dyna 130HT sebesar
5.615 BCM/bulan. Produksi alat muat maupun alat angkut pada saat ini belum
mencapai target produksi yang ditetapkan oleh perusahaan.
Upaya peningkatan produksi dilakukan dengan mengubah pola pemuatan,
mengganti bucket excavator dan meningkatkan efisiensi kerja dan perbaikan waktu
edar pada alat angkut. Setelah dilakukan penekanan terhadap waktu hambatan,
efisiensi kerja mengalami peningkatan, pada alat muat meningkat dari 5,56 jam/hari
menjadi 6,70 jam/hari, pada alat angkut meningkat dari 5,74 jam/hari menjadi
6,41 jam/hari. Serta perbaikan waktu edar alat angkut dengan menambah kecepatan
alat angkut pasa saat membawa muatan dan pada saat kembali kosong, sehingga
waktu edar alat angkut meningkat dari 63,54 menit menjadi 48,62 menit, dengan
adanya perbaikan-perbaikan tersebut dapat meningkatkan kemampuan produksi alat
muat menjadi 11.173 BCM/bulan dan alat angkut menjadi 7.299 BCM/bulan,
dengan begitu target produksi yang telah ditetapkan oleh perusahaan dapat
terpenuhi.
vi
SUMMARY
CV. Muncul Karya was one of the companies engaged in Andesite mining in
Sidomulyo Village, Pengasih District, Kulon Progo Regency, DIY. The mining
system applied by the company was open-pit mining with the quarry method. These
activities consist of excavation, loading, and hauling. Excavation activities were
carried out by rock breakers, loaded was carried out by excavators, and the hauled
processed was carried out by dump trucks. The problem faced by the company was
that the andesite production target of 7,000 BCM/month had not been achieved.
The planned andesite mining production target had not been achieved, Therefore,
it was necessary to analyze the factors and obstacles that had caused the production
target to had not been achieved and made efforts to achieve the production target.
The research method applied in this study was started from the literature
study and direct observation in the field for primary and secondary data collection.
The next step was to processed the data obtained from the field and conduct data
analyzed. The factors that affect andesite production activities were the low value
of the bucket fill factor 60%, the low efficiency of the tool work on loaded equipment
by 69% and on hauled equipment by 72%, and the presence of overburden material
inside of the front mining which caused narrow space for the dump truck to
maneuver, so that there was a waited time for the loading equipment when the dump
truck took a position to be loaded.
The production of andesite mining at the company at this time was for 1 unit
of loaded equipment KOMATSU PC200 of 4,827 BCM/month and for 10 units of
dump truck Toyota Dyna 130HT of 5,615 BCM/month. Currently, the production
of loaded equipment and hauled equipment had not reached the production target
set by the company.
Efforts to increase andesite production were carried out by changed loading
patterns, replacing excavator buckets, and increasing work efficiency and improved
cycle times on dump truck. After emphasizing the inhibition time, work efficiency
had increased. Work efficiency on loading equipment increased from 5.56
hours/day to 6.70 hours/day. Work efficiency on dump truck increased from 5.74
hours/day to 6.41 hours/day. Improvements to the hauling equipment cycle time
were carried out by increasing the speed of the hauling equipment when carrying
the load and when it was empty again, so that the hauled equipment cycle time
increases from 63.54 minutes to 48.62 minutes. These improvements were able to
increase the production capacity of loading equipment to 11,173 BCM/month and
hauling equipment to 7,299 BCM/month. Thus, the production targets set by the
company could be met.

Item Type: Thesis (Other)
Uncontrolled Keywords: pertambangan batu Andesit
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: Faculty of Engineering, Science and Mathematics > School of Engineering Sciences
Depositing User: Eko Yuli
Date Deposited: 29 Mar 2022 02:25
Last Modified: 16 Sep 2022 06:34
URI: http://eprints.upnyk.ac.id/id/eprint/29262

Actions (login required)

View Item View Item