PENENTUAN STRATEGI PEMELIHARAAN MESIN CNC 3 AXIS DOUBLE COLUMN DENGAN PENDEKATAN RELIABILITY CENTERED MAINTENANCE (RCM)

Suryanegara, Wisanggeni (2021) PENENTUAN STRATEGI PEMELIHARAAN MESIN CNC 3 AXIS DOUBLE COLUMN DENGAN PENDEKATAN RELIABILITY CENTERED MAINTENANCE (RCM). Diploma thesis, UPN "Veteran" Yogyakarta.

[thumbnail of 1. Skripsi Full.pdf] Text
1. Skripsi Full.pdf
Restricted to Repository staff only

Download (4MB)
[thumbnail of 2. Abstrak.pdf]
Preview
Text
2. Abstrak.pdf

Download (108kB) | Preview
[thumbnail of 3. Cover.pdf]
Preview
Text
3. Cover.pdf

Download (68kB) | Preview
[thumbnail of 4. Lembar Pengesahan.pdf]
Preview
Text
4. Lembar Pengesahan.pdf

Download (325kB) | Preview
[thumbnail of 5. Daftar Isi.pdf]
Preview
Text
5. Daftar Isi.pdf

Download (174kB) | Preview
[thumbnail of 6. Daftar Pustaka.pdf]
Preview
Text
6. Daftar Pustaka.pdf

Download (122kB) | Preview
[thumbnail of 6. Daftar Pustaka.pdf]
Preview
Text
6. Daftar Pustaka.pdf

Download (122kB) | Preview

Abstract

ABSTRAK

PT YPTI merupakan perusahaan yang bergerak dibidang industri manufaktur
dengan mengandalkan mesin CNC sebagai mesin produksinya. Divisi maintenance PT
YPTI masih menerapkan sistem corrective maintenance dan tidak memiliki persediaan
spare part yang pasti. Berdasarkan data historis kerusakan mesin selama periode
Januari 2018 – Desember 2019 mesin Hartford 3150 mengalami 34 kali kerusakan,
mesin Hartford 3210 13 kali kerusakan dan Hartford 4210 20 kali kerusakan. Sering
kali ditemukan kasus dimana terjadi kerusakan part mesin pada saat shift kedua
pada malam hari namun tidak dapat diperbaiki saat itu juga dikarenakan Divisi
Maintenace PT YPTI hanya bekerja pada shift pertama pada pagi hingga sore hari
saja. Apabila kerusakan mesin tersebut membutuhkan penggantian part, maka akan
langsung dilganti selama spare part yang dibutuhkan tersedia, akan tetapi jika tidak
tersedia maka akan dilakukan pembelian yang menambah lamanya downtime
mesin.
Penelitian ini bertujuan untuk menentukan stratgei pemeliharaan berdasarkan rataata

waktu antar kerusakan mesin dengan pendekatan Reliability Centered Maintenance
RCM). Dari strategi pemeliharaan tersebut diperoleh interval waktu preventive
maintenance mesin, perhitungan biaya pemeliharaan dan perencanaan persediaan spare
part. Sehingga dapat mencegah terjadinya kerusakan pada shift kedua dan dapat
mempersiapkan kebutuhan spare partnya agar meminimalisir terjadinya downtime.
Berdasarkan hasil pengolahan data interval waktu preventive maintenance untuk
mesin Hartford 3150 selama 20 hari, Hartford 3210 selama 56 hari, dan Hartford 4210
selama 35 hari. Total biaya pemeliharaan untuk satu tahun, mesin Hartford 3150 senilai
Rp. 61.466.925,00, Hartford 3210 senilai Rp. 42.526.191,00, Hartford 4210 senilai Rp.
35.288.601,00. Persediaan spare part dalam jangka waktu satu tahun untuk part flexible
coupling sebanyak 24 pcs, bearing sebanyak 9 pcs, oil seal sebanyak 12 pcs, dan air hose
pneumatic sepanjang 50 meter.

Kata kunci: Pemeliharaan, preventive maintenance, RCM, downtime, interval waktu
penggantian

ABSTRACT

PT YPTI is a company engaged in the manufacturing industry by relying on CNC
machines as production machines. The maintenance division still applies the corrective
maintenance system and does not have a definite inventory of spare parts. Based on
historical data of machine failures during the period January 2018 - December 2019, the
Hartford 3150 machine suffered 34 damage, the Hartford 3210 engine was damaged 13
times and the Hartford 4210 malfunctioned 20 times. Oftentimes there are cases where
there is damage to machine parts during the second shift at night but it cannot be repaired
at that time because PT YPTI's Maintenance Division only works the first shift in the
morning to evening only. If the machine failure requires a part replacement, it will be
replaced immediately as long as the required spare part is available, but if it is not
available, a purchase will be made which increases the length of machine downtime.
This study aims to determine the maintenance strategy based on the average time
between machine failures using the Reliability Centered Maintenance (RCM) approach.
From this maintenance strategy, it is obtained the machine preventive maintenance time
interval, the calculation of maintenance costs and spare part inventory planning. So that it
can prevent damage to the second shift and can prepare the needs of its spare parts in
order to minimize downtime.
Based on the results of preventive maintenance time interval data processing for
the Hartford 3150 machine for 20 days, Hartford 3210 for 56 days, and Hartford 4210 for
35 days. The total maintenance cost for one year, the Hartford 3150 machine is valued at
Rp. 61,466,925.00, Hartford 3210 valued at Rp. 42,526,191.00, Hartford 4210 valued at
Rp. 35,288,601.00. Supply of spare parts for a period of one year for flexible coupling parts
of 24 pcs, 9 pcs of bearings, 12 pcs of oil seals, and 50 meters of air hose pneumatic.

Keywords: maintenance, preventive maintenance, RCM, downtime, replacement time
intervals

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Pemeliharaan, preventive maintenance, RCM, downtime, interval waktu penggantian
Subjek: T Technology > TK Electrical engineering. Electronics Nuclear engineering
Divisions: x. Faculty of Engineering, Science and Mathematics > School of Engineering Sciences
Depositing User: Eny Suparny
Date Deposited: 04 Mar 2022 02:48
Last Modified: 04 Mar 2022 02:48
URI: http://eprints.upnyk.ac.id/id/eprint/28588

Actions (login required)

View Item View Item