PENINGKATAN PRODUKTIFITAS DAN KESELARASAN KERJA UNIT AGITATOR TRUCK DAN SPRAYMEC UNTUK MEMENUHI TARGET PRODUKSI SHOTCRETE KENCANA UNDERGROUND PT. NUSA HALMAHERA MINERALS

NABIU, ANDRIO FADHIL JAMAL (2014) PENINGKATAN PRODUKTIFITAS DAN KESELARASAN KERJA UNIT AGITATOR TRUCK DAN SPRAYMEC UNTUK MEMENUHI TARGET PRODUKSI SHOTCRETE KENCANA UNDERGROUND PT. NUSA HALMAHERA MINERALS. Other thesis, UPN "Veteran" Yogyakarta.

[thumbnail of RINGKASAN.pdf]
Preview
Text
RINGKASAN.pdf

Download (50kB) | Preview

Abstract

RINGKASAN
PT. Nusa Halmahera Minerals (PT. NHM) adalah perusahaan tambang
emas atau yang dikenal dengan Gosowong Gold Mine berada dibelahan timur
lengan utara Pulau Halmahera, Provinsi Maluku Utara dengan koordinat 1
o
27’ N
dan 128
o
30’ E. Jalan Trans Halmahera menghubungkan Sidangoli dan Tambang
Emas Gosowong dengan jalan aspal yang ditempuh mobil dalam waktu 5-6 jam.
Jarak lurus dari Ternate, Ibukota Provinsi Maluku Utara adalah 55 km, yang dapat
ditempuh dengan chopper atau pesawat dalam waktu7-8 menit.
PT. NHM memiliki tiga lokasi penambangan, yaitu Gosowong Pit,
Kencana Underground, dan Toguraci Underground. Untuk saat ini lokasi
penambangan yang masih aktif beroperasi adalah Kencana Underground dan
Toguraci Underground. Lokasi Gosowong Pit sudah tidak beroperasi lagi di tahun
2011 dikarenakan umur tambang nya sudah habis. Sedangkan untuk lokasi
Kencana Underground memiliki target produksi bijih sebesar 66.084 ton pada
Bulan Juni 2014 dan target produksi pada lokasi Toguraci Underground adalah
sebesar 43.564 ton pada Bulan Juni 2014.
PT. NHM menggunakan dua sistem penambangan, yaitu sistem tambang
terbuka dan sistem tambang bawah tanah. Metode yang digunakan pada tambang
bawah tanah PT. NHM adalah Underhand Cut And Fill dan Long Hole Stoping.
Sistem tambang tanah, terutama yang menggunakan metode Underhand Cut And
Fill dan Long Hole Stoping membutuhkan penyanggaan agar tidak terjadi
longsoran pada terowongan yang dibuat. Sistem penyanggan pada PT. NHM
menggunakan tiga jenis penyanggaan, yaitu baut batuan (rock bolt), jaring kawat
(weld mesh), dan juga beton tembak (shotcrete). Untuk sistem penyanggaan
menggunakan shotcrete, perlu adanya peralatan mekanis untuk mendistribusikan
shotcrete. Peralatan mekanis yang dipakai adalah Agitator Truck Normet LF 600
dan Spraymec Normet WP 1080. Target produksi shotcrete dari perusahaan adalah
sebesar 62,1 m
3
/hari. Produksi aktual shotcrete saat ini adalah sebesar 35 m
3
/hari.
Produktifitas teoritis Agitator Truck adalah sebesar 35,74 m
3
/hari dan
produktifitas teoritis Spraymec sebesar 19,65 m
3
/hari. Kekurangan yang terjadi
saat ini adalah sebesar 27,1 m
3
/hari. Kekurangan produksi aktual yang terjadi
disebabkan oleh adanya faktor teknis dan faktor non teknis yang terjadi selama
pendistribusian shotcrete menuju heading yang akan dilakukan penyanggaan.
Kajian tentang faktor kendala yang menyebabkan target produksi tidak
tercapai harus dilakukan agar kebutuhan shotcrete sebagai penyangga utama
terowongan dapat terpenuhi. Setelah dilakukan kajian tentang faktor kendala yang
terjadi, maka produktifitas Agitator Truck menjadi 70,38 m
3
/hari. Sedangkan
untuk Spraymec meningkat menjadi 43,08 m
3
/hari. Rendahnya produktifitas
Spraymec disebabkan tinggi nya waktu kerusakan alat. Penurunan waktu delay
atau pengoptimalan faktor kendala yang terjadi menyebabkan target produksi
shotcrete terpenuhi.

ABSTRACT
Nusa Halmahera Mining Limited which is famous by Gosowong Gold
Mine Project is located in the east parts of nothern arm of North Malocco
Province has coordinates on 1
o
27’ N dan 128
o
30’ E. Sidangoli and Gosowong
Gold Mine are connected by trans Halmahera Street and can be reached by car
about 5-6 hours. The distance from Ternate (Capital City of North Malocco) to
Gosowong Gold Mine is about 55 kms and can be reached by chopper or plane
about 7-8 minutes.
Nusa Halmahera Mining Limited has three mining location. These three
location are Gosowong Pit, Kencana Underground, and Toguraci Underground.
By this time, only Kencana Underground and Toguraci Underground are
operating, whereas Gosowong Pit no longer operating and stopped in 2011.
Gosowong Pit no longer operating because of mine out. Kencana Underground
has 66.084 tones of ore production target in June 2014 and Toguraci Underground
has 43.564 tones of ore production target in June 2014.
Nusa Halmahera Mining Limited use two mining systems. These are
Surface Mining and Underground Mining system. The method that used in the
underground system is Underhand Cut and Fill and Long Hole Stoping. These two
methods requires a tunneling support to avoid the risk in the tunnel that was made.
The company use three types of tunneling support, there are rock bolt, weld mesh,
and shotcrete. The shotcrete supporting types requires a mechanical equipment in
order to distribute shotcrete. The mechanical equipment that used by the company
are Agitator Truck Normet LF 600 and Spraymec Normet WP 1080. The
production target of shotcrete is 62.1 m
3
/day. By this time the actual production of
shotcrete is 35 m
3
/day. Whereas the teoritical production of Agitator Truck is
35.74 m
3
/day. The teoritical productivity of Spraymec which is a loading
equipment of shotcrete is 19.65 m
3
/day. There is a different between the actual
production of shotcrete and the production target of shotcrete.
The shortage of actual production occurs due to technical factors and non
technical factors that occurs during the distribution of shotcrete.
Studies on constraint factors that cause the low actual production must be
done so the requirements of shotcrete as the main support of the tunnel buffering
can be fulfilled. After a study of the factors that caused a low actual production of
shotcrete occurs, the productivity of Agitator Truck amounted to 70.38 m
3
/day
and for Spraymec amounted to 43.08 m
3
/day. The low production of Spraymec is
caused by the high value of breakdown time. By reducing the delay time or
optimization constraint factors that occur are able to fulfill Kencana shotcrete
requirements.

Item Type: Thesis (Other)
Subjek: T Technology > TN Mining engineering. Metallurgy
Divisions: x. Faculty of Engineering, Science and Mathematics > School of Engineering Sciences
Depositing User: Ratna Sufiatin
Date Deposited: 23 May 2016 03:28
Last Modified: 23 May 2016 03:28
URI: http://eprints.upnyk.ac.id/id/eprint/2048

Actions (login required)

View Item View Item