BAWONO, SAN NIR WESTY POPPY (2014) RENCANA TEKNIS PENCEGAHAN AIR ASAM TAMBANG DENGAN METODE ENCAPSULATION PADA PIT 3000 BLOCK 5 SOUTH BLOCK DI PT. TRUBAINDO COAL MINING KABUPATEN KUTAI BARAT KALIMANTAN TIMUR. Other thesis, UPN "Veteran" Yogyakarta.
Preview |
Text
ABSTRACT.pdf Download (83kB) | Preview |
Abstract
PT. Trubaindo Coal Mining (PT. TCM) merupakan perusahaan yang bergerak
dalam bidang pertambangan batubara yang lokasinya secara administratif
berlokasi di Kecamatan Melak, Kabupaten Kutai Barat, Provinsi Kalimantan
Timur. PT. TCM menggunakan sistem penambangan strip mine yang secara
langsung maupun tidak langsung dapat mengubah bentuk bentang alam di sekitar
lokasi penambangan. PT. TCM merencanakan melakukan kegiatan penambangan
di South Block pada dua Pit, yakni Pit 2600 Block 5 (P2600Bk05) dan Pit 3000
Block 5 (P3000Bk05) dengan memindahkan material tanah penutup (Overburden
atau OB) sebanyak 8.064.200 BCM, dan sebanyak 185.300 BCM atau sekitar
2,3% dari total OB yang akan dipindahkan terkategorikan sebagai material
Potential Acid Forming (PAF) dan 7.878.900 BCM atau 97,7% merupakan Non
Acid Forming (NAF).
Air Asam Tambang terbentuk akibat terjadinya proses oksidasi antara mineral
sulfide, air, dan udara, sehingga harus dilakukan pencegahan agar tidak terjadi
kontak antara ketiga elemen tersebut. Pencegahan yang dapat dilakukan adalah
dengan melakukan penanganan terhadap tanah penutup yang berpotensi
pembentuk asam.
Dalam mencegah terbentuknya Air Asam Tambang, maka timbunan
(penempatan) material PAF dan NAF tersebut haruslah direncanakan dan
dijadwalkan dengan baik. Desain timbunan terpengaruh oleh beberapa faktor,
yaitu :
1. Jumlah dan persentase material batuan penutup yang akan ditimbun.
2. Topografi daerah penimbunan.
Lokasi penimbunan yang digunakan adalah inpit dump (material tanah penutup
ditimbun kembali ke lokasi pit yang telah selesai digali) yaitu di Ex-Pit 3000
Block 7 dan lokasi outpit dump (material tanah penutup ditimbun di luar pit) yaitu
di jalan Hauling. Metode yang digunakan untuk menangani material PAF adalah
Metode Kapsulasi PAF yaitu menempatkan material PAF di dalam disposal dan
dilapisi oleh material NAF. SOP PT. TCM menentukan bahwa tebal NAF untuk
kapsulasi adalah 3 m, namun dalam penelitian ini disimpulkan bahwa sebenarnya
material NAF dapat melapisi PAF dengan ketebalan lebih dari 3 m yaitu 5 m,
bahkan hingga 10 m karena material NAF yang terdapat pada tanah penutup yang
akan dipindahkan oleh PT. TCM mencukupi untuk membentuk lapisan tersebut
(Volume NAF 7.878.900 BCM atau 97,7% dari keseluruhan volume tanah
penutup).
PT. Trubainco Coal Mining (PT. TCM) is a company engaged in coal mining
which are located administratively included in the Subdistrict of Melak, West
Kutai Regency, East Kalimantan Province. PT. TCM using open pit mining
system with strip mine method that directly or indirectly can change the natural
landscape surrounding the mining. PT. TCM planned mining operation in South
Block on two Pit, on Pit 2600 Block 5 (P2600Bk05) and Pit 3000 Block 5
(P3000Bk05) to move the overburden material (overburden or OB) as much as
8.064.200 BCM, and as much as 185.300 BCM or approximately 2,3% of total
OB to be moved is classified as material Potential Acid Forming (PAF) and
7.878.000 BCM or 97,7% are Non Acid Forming (NAF).
Acid Mine Drainage is formed due to the oxidation processes include sulfide
minerals, water, and air, so it must be done in order to avoid the preventation of
contact between these elements. Prevention that can be done is to make the
handling of the Potential Acid Forming materials.
In preventing the formation of Acid Mine Drainage, the placement of PAF and
NAF materials must be planned and scheduled well. Disposal design influenced
by several factors, that is :
1. Amount and percentage of overburden material will be disposed.
2. Topography of the disposal area
Hoarding location used is inpit dump (overburden material backfilled pit in the
location that has been finished pit) that is on Ex-Pit 3000 Block 7 and outpit dump
location (overburden material disposed outside the pit) that is on hauling road.
The method used to handle PAF materials was encapsulation method by placing
the PAF materials and covered by the NAF materials. PT. TCM SOP determines
that the thickness of NAF that used to the encapsulation method was 3 m, but in
this research it was found that in fact they can capsulating the PAF material with a
thickness of more than 3 m, is a minimum thickness of 5 m, even up to 10 m
because NAF material contained on overburden is sufficient to form the layer
(NAF volume 7.878.900 BCM or 97,7% of the total overburden volume).
Item Type: | Thesis (Other) |
---|---|
Subjek: | T Technology > TN Mining engineering. Metallurgy |
Divisions: | x. Faculty of Engineering, Science and Mathematics > School of Engineering Sciences |
Depositing User: | Eko Suprapti |
Date Deposited: | 20 May 2016 06:22 |
Last Modified: | 20 May 2016 06:22 |
URI: | http://eprints.upnyk.ac.id/id/eprint/1940 |
Actions (login required)
![]() |
View Item |