ANALISIS PRODUKTIVITAS ALAT MUAT DAN ALAT ANGKUT DENGAN MENGGUNAKAN METODE ANTRIAN PADA KEGIATAN PENGUPASAN LAPISAN TANAH PENUTUP DI PIT 13W PT. TAMBANG RAYA USAHA TAMA SITE IMM BONTANG KALIMANTAN TIMUR

Romadhon, Arief Khoirru (2019) ANALISIS PRODUKTIVITAS ALAT MUAT DAN ALAT ANGKUT DENGAN MENGGUNAKAN METODE ANTRIAN PADA KEGIATAN PENGUPASAN LAPISAN TANAH PENUTUP DI PIT 13W PT. TAMBANG RAYA USAHA TAMA SITE IMM BONTANG KALIMANTAN TIMUR. Other thesis, Universitas Pembangunan Nasional Veteran Yogyakarta.

[img]
Preview
Text
Cover.pdf

Download (113kB) | Preview
[img]
Preview
Text
Lembar Pengesahan.pdf

Download (380kB) | Preview
[img]
Preview
Text
Abstrak.pdf

Download (512kB) | Preview
[img]
Preview
Text
Daftar isi.pdf

Download (133kB) | Preview

Abstract

RINGKASAN Penambangan batubara PT. Tambang Raya Usaha Tama site Indominco Mandiri di Pit 13W dilakukan dengan sistem tambang terbuka metode strip mine. Sebelum dilakukan penambangan batubara dilakukan kegiatan pengupasan lapisan tanah penutup (overburden) menggunakan alat muat backhoe Komatsu PC-1250 SP yang dikombinasikan dengan alat angkut Komatsu HD-465 TR. Target produktifitas pengupasan lapisan tanah penutup adalah 550 bcm/jam. Produktivitas saat ini sebesar 486 BCM/jam, sehingga masih terdapat kekurangan target produksi sebesar 64 BCM/jam. Kekurangan target produksi terjadi karena antrian pada tahap pelayanan di loading point menyebabkan adanya waktu tunggu yang menambah waktu edar. Waktu tunggu di loading point A adalah 2,031 menit, loading point B adalah 2,051 menit dan loading point C adalah 1,846 menit. Perlu dilakukan alternatif pencapaian produksi dengan melakukan penggunaan metode double backup, penggunaan bulldozer di loading point dan perbaikan pada segmen jalan angkut. Setelah dilakukan alternatif pencapaian produksi, waktu tunggu menjadi 1,163 menit di loading point A, 1,087 menit di loading point B dan 0,782 menit di loading point C. Hasil alternatif pencapaian produksi diperoleh nilai produktifitas sebesar 559,6 BCM/jam. ABSTRACT Coal mining activities at PT. Tambang Raya Usaha Tama site Indominco Mandiri in Pit 13W using open mine system and strip mine method. Before start the coal mining activities, overburden was carried out using backhoe Komatsu PC-1250 SP that combined with dumptruck Komatsu HD-465 TR. Target productivity of overburden stripping activities was 550 BCM / hour. Current productivity of overburden stripping activities was 486 BCM / hour, so there is some lack of productivity targets about 64 BCM / hour. Lack of productivity target occurs because the queue at the service phase in the loading point causes a waiting time that adds the circulation time. Waiting time at loading point A was 2.031 minutes, loading point B was 2.051 minutes and loading point C was 1.846 minutes. Alternative production needs to be done by using the double backup method, using a bulldozer in loading points and repairing the haul road segment. After alternative production done, the waiting time becomes 1.163 minutes at loading point A, 1.087 minutes at loading point B and 0.782 minutes at loading point C. The alternative production make productivity result increase to 559.6 BCM / hour.

Item Type: Thesis (Other)
Subjects: T Technology > T Technology (General)
Divisions: Faculty of Engineering, Science and Mathematics > School of Engineering Sciences