SETIAWAN, FAJAR BUDI (2018) KAJIAN TEKNIS KINERJA ALAT GALI MUAT DAN ALAT ANGKUT PADA KEGIATAN PENAMBANGAN BATUBARA DI BLOCK B PT. MINEMEX INDONESIA MANDIANGIN KABUPATEN SAROLANGUN PROVINSI JAMBI. Other thesis, UPN "Veteran" Yogyakarta.
Preview |
Text
COVER.pdf Download (249kB) | Preview |
Preview |
Text
ABSTRACT.pdf Download (6kB) | Preview |
Preview |
Text
LEMBAR_PENGESAHAN.pdf Download (4MB) | Preview |
Preview |
Text
DAFTAR_ISI.pdf Download (164kB) | Preview |
Text
daftar pustaka.pdf Download (316kB) |
Abstract
PT. Minemex Indonesia ( PT. MMI ) is a company that focusing on coal
mining field. Mining location of PT. Minemex Indonesia ( PT. MMI ) is in
Mandiangin sub district of Sarolangun Regency in Jambi Province. Activities of
coal transportation of PT. Minemex Indonesia ( PT. MMI ) at Block B is using
mechanical Equipments such as Kobelco SK 330-8 and Mitsubishi 220 PS FN 527
ML. The Distance between front mining place to stockyard is approximated 1800
meters.
PT.MMI have production target of coal mining in block B is 90.000 ton per
months. Mean while the production can be reach until now is 70.000 ton per
months. The unreached production of Block B of PT. Minemex Indonesia ( PT.
MMI) coal mining caused of work efficiency that not optimal yet, the condition of
haul road, and excavators with insufficient production capacity.
At the time of the research PT MMI use 1 loading equipment and 5 hauler
equipment with match factor 1,09 efficiency 79,9 % and 83 %. The houling road
has 7 meters width.
The efforts to reach the coal mining productions target of Block B is by
increasing work time effectively so that increases the efficiency of equipments
become 82 % in loading equipment and efficiency of hauler equipment become 86
%, mend the haul road geometry for optimal transportation of conveyans from 20,5
minutes of cycle time to 18 minutes. Mean while huling by hauler become obtained.
The production after repaired in work time effectively and mend the haul
road geometry increase 74.000 ton per month with an increase under production
target. So need to added more loading equipment to reach production target and for
balancing hauler production, mean while the production will get by theoretical is
123.000 ton per months
Item Type: | Thesis (Other) |
---|---|
Subjects: | T Technology > TA Engineering (General). Civil engineering (General) |
Divisions: | Faculty of Engineering, Science and Mathematics > School of Engineering Sciences |
Depositing User: | Eko Yuli |
Date Deposited: | 18 Oct 2018 02:16 |
Last Modified: | 29 Feb 2024 02:56 |
URI: | http://eprints.upnyk.ac.id/id/eprint/17017 |